Actual vs Allocated Hours

Advice appreciated on overlaying allocated hours on actual hours. Scenario: currently using PowerBI to summarise the time spent on help desk tickets by client by month. Clients pay a monthly fee for...
  • vanessafvg's avatar
    vanessafvg
    5 years ago

    here are some examples of what you can do, it also depends if you want to use a custom chart or a default chart , i mostly only use default visuals.

     

    file attached.

     

     

     

  • Anonymous's avatar
    Anonymous
    5 years ago

    Hi NexusProjects ,

     

    You could use Line and Stacked column chart together with Conditional Formatting:

    1.calculate the sum of actual time for each client:

    Sum Measure = CALCULATE(SUM('Tickets (Actual)'[Time]),FILTER('Tickets (Estimated)','Tickets (Estimated)'[Client]=MAX('Tickets (Actual)'[Client])))

    2.If Actual time >AllocatedTime ,then set red color, otherwise green:

    color measure = IF([Sum Measure]>MAX('Tickets (Estimated)'[AllocatedTime]),"Red","Green") 

     3.Create visuals:

    Below is the final output:

     

    Or you could import more visual types to get a more suitable visual such as Overlapping Bar chart, LipStack column chart as shown below:

     

    Best Regards,
    Eyelyn Qin