Construction Project dashboard

This interactive report contains the most common activities in the construction projects along with their productivity rates hours per unit, a detailed description of the activity, activity predecessor, and activity successor.  Each construction activity has a photo to give you an understanding of the construction projects sequence of work and know more about construction productivity.

 

 

How does it work?

1- Select the activity division of work or search for an activity in the search box.

2- Select the activity you want to see its information by clicking on an activity in the activity name box.

3- The following data will data will be filtered based on the selected activity:

  • Crew Details and productivity rates.
  • Predecessor description and photo.
  • Successor description and photo.

 

Best Regards from Planning Engineer