The syntax error

PC2022_0-1731009545727.png

Please tell me what i am doing wrong. Thank you.

 

SchKPI =
VAR DaysUntil = DATEDIFF(today(), msdyn_projecttask[Finish], DAY)

VAR ScheduleStatus = SWITCH(TRUE(),
(msdyn_projecttask[% Complete]<100 && DaysUntil < 0) || msdyn_projecttask[Finish] > msdyn_projecttask[Baseline Finish], "Off Schedule",
msdyn_projecttask[% Complete]<100 && DaysUntil < 45, "On Watch",
msdyn_projecttask[Finish] <= msdyn_projecttask[Baseline Finish], "On Schedule",
"Error")
1 ACCEPTED SOLUTION
lbendlin
Super User
Super User

You are missing the RETURN statement.

View solution in original post

2 REPLIES 2
lbendlin
Super User
Super User

You are missing the RETURN statement.

Thank you!

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.