Hello everyone!
I would like to add a line to my bar chart to show the daily target for our sales.
The budget has the granularity of weeks. Now I need to divide this amount by the working days per week.
For this purpose, I added a WorkingDay (1 / 0) column in the calendar table.
Now, how would you calculate the daily budget?
Have you tried dividing the weekly budget by the sum of your workingday column for the given week? I assume you flag holidays too?
Check out the November 2025 Power BI update to learn about new features.
Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!
| User | Count |
|---|---|
| 11 | |
| 9 | |
| 9 | |
| 6 | |
| 5 |
| User | Count |
|---|---|
| 27 | |
| 22 | |
| 19 | |
| 17 | |
| 11 |