Hi,
According to your description, I can roughly understand your requirement, I think you can try this measure to apply as the conditional format for the column [Completed data] to achieve your requirement:
This is the test data I used:
Due Date = 'Table'[Date Received]+3Then create a measure like this:
Color = IF( MAX('Table'[Date completed])<>BLANK(), IF(MAX('Table'[Date completed])>MAX('Table'[Due Date]),"Red","White"), "Red")Then you can set the conditional format for the field [Completed data] like this:
And you can get what you want, like this:
You can download my test pbix file below
If this result is not what you want, you can post some sample data(without sensitive data) and your expected result.
How to Get Your Question Answered Quickly
Thank you very much!
Best Regards,
Community Support Team _Robert Qin
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.