Do you mean like this?
Skill Count = CALCULATE ( SUMX ( SUMMARIZE ( 'Table', 'Table'[Employee Name], 'Table'[Skill Name], 'Table'[Status] ), IF ( CALCULATE ( MAX ( 'Table'[Date/Time] ) ) = CALCULATE ( MAX ( 'Table'[Date/Time] ), ALL ( 'Table'[Date/Time], 'Table'[Status] ), ALL ( 'Status' ) ), 1 ) ), 'Date'[Date] <= MAX ( 'Date'[Date] ) )
Hi Anonymous
Please provide more examples
In the table below Employee 1 has 11 unique Skill Names, which you can see has multiple Status per Skill Name and some have repeated values from changing of those statuses. With a slicer selected as Status = Not Verified, the total should show 7 by returning back 1 Status with the Status as Not Verified per Skill Name. Because that Status can be multiple times per Skill Name, the latest Date/Time should be selected.
| Employee Name | Skill Name | Status | Date/Time |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Adaptability & Flexibility | Verified | 8/21/19 12:20 |
| Employee 1 | Managing Work | Verified | 8/21/19 12:20 |
| Employee 1 | Senior / Lead Claim Processing Technician | Not verified | 8/21/19 12:20 |
| Employee 1 | Adaptability & Flexibility | Submitted | 8/22/19 17:12 |
| Employee 1 | Quality Orientation | Not verified | 9/24/19 20:27 |
| Employee 1 | Initiating Action | Submitted | 9/24/19 20:27 |
| Employee 1 | Quality Orientation | Submitted | 9/24/19 20:27 |
| Employee 1 | System Architecture | Submitted | 9/24/19 20:27 |
| Employee 2 | Quality Orientation | Submitted | 9/24/19 20:28 |
| Employee 2 | Senior / Lead Claim Processing Technician | Submitted | 9/24/19 20:28 |
| Employee 2 | System Architecture | Submitted | 9/24/19 20:28 |
| Employee 1 | System Architecture | Verified | 10/14/19 19:18 |
| Employee 1 | Quality Orientation | Not verified | 10/14/19 19:18 |
| Employee 1 | Senior / Lead Claim Processing Technician | Submitted | 10/15/19 1:39 |
| Employee 3 | Quality Orientation | Not verified | 10/16/19 16:21 |
| Employee 3 | System Architecture | Verified | 10/16/19 16:21 |
| Employee 1 | Active Listening | Not verified | 10/17/19 22:34 |
| Employee 1 | Responsible | Not verified | 10/17/19 22:34 |
| Employee 1 | Stress Tolerance | Not verified | 10/17/19 22:34 |
| Employee 1 | High School Diploma or equivalent | Not verified | 10/23/19 19:21 |
| Employee 4 | Infrastructure | Submitted | 11/14/19 17:35 |
| Employee 4 | Presenting & Communicating Information | Submitted | 11/14/19 17:35 |
Here is the same table but with only Employee 1 and sorted by Skill Name then Date/Time to more easily understand the example above. The table above was sorted by Date/Time as it would normally appear.
| Employee Name | Skill Name | Status | Date/Time |
| Employee 1 | Active Listening | Not verified | 10/17/19 22:34 |
| Employee 1 | Adaptability & Flexibility | Submitted | 8/22/19 17:12 |
| Employee 1 | Adaptability & Flexibility | Verified | 8/21/19 12:20 |
| Employee 1 | High School Diploma or equivalent | Not verified | 10/23/19 19:21 |
| Employee 1 | Initiating Action | Submitted | 9/24/19 20:27 |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Interpersonal | Not verified | 8/21/19 12:17 |
| Employee 1 | Managing Work | Verified | 8/21/19 12:20 |
| Employee 1 | Quality Orientation | Not verified | 10/14/19 19:18 |
| Employee 1 | Quality Orientation | Submitted | 9/24/19 20:27 |
| Employee 1 | Quality Orientation | Not verified | 9/24/19 20:27 |
| Employee 1 | Responsible | Not verified | 10/17/19 22:34 |
| Employee 1 | Senior / Lead Claim Processing Technician | Submitted | 10/15/19 1:39 |
| Employee 1 | Senior / Lead Claim Processing Technician | Not verified | 8/21/19 12:20 |
| Employee 1 | Stress Tolerance | Not verified | 10/17/19 22:34 |
| Employee 1 | System Architecture | Verified | 10/14/19 19:18 |
| Employee 1 | System Architecture | Submitted | 9/24/19 20:27 |
- tamerj13 years ago
Community Champion
Anonymous
Ok, that does not match with your initial description. Kindly provide your red markups on below proposal's screenshots.- Anonymous3 years agoNot applicable
In your two examples, the total should be the sum of all employees for that status.
Example 1:
Employee 1 = 7 + Employee 3 = 1 == Total = 8
Example 2:
Employee 1 = 5 + Employee 2 = 3 + Employee 4 = 2 == Total = 10
In addition in your first table, you can see that for the skill Quality Orientation you are returning two values for Not Verified. There are two values of Not Verified for that Skill but I only need the latest status and only counting that 1.
In the example that I provided for Employee 1, I've highlighted below the skills that should be counted for Not Verified:
Employee Name Skill Name Status Date/Time Employee 1 Active Listening Not verified 10/17/19 22:34 Employee 1 Adaptability & Flexibility Verified 8/21/19 12:20 Employee 1 Adaptability & Flexibility Submitted 8/22/19 17:12 Employee 1 High School Diploma or equivalent Not verified 10/23/19 19:21 Employee 1 Initiating Action Submitted 9/24/19 20:27 Employee 1 Interpersonal Not verified 8/21/19 12:17 Employee 1 Interpersonal Not verified 8/21/19 12:17 Employee 1 Interpersonal Not verified 8/21/19 12:17 Employee 1 Managing Work Verified 8/21/19 12:20 Employee 1 Quality Orientation Not verified 9/24/19 20:27 Employee 1 Quality Orientation Submitted 9/24/19 20:27 Employee 1 Quality Orientation Not verified 10/14/19 19:18 Employee 1 Responsible Not verified 10/17/19 22:34 Employee 1 Senior / Lead Claim Processing Technician Not verified 8/21/19 12:20 Employee 1 Senior / Lead Claim Processing Technician Submitted 10/15/19 1:39 Employee 1 Stress Tolerance Not verified 10/17/19 22:34 Employee 1 System Architecture Submitted 9/24/19 20:27 Employee 1 System Architecture Verified 10/14/19 19:18 I also made an error before, the total for Not Verified should be 6. I counted an extra one because I had the dates sorted the wrong way. The most recent status needs to be Not Verified for it to count. You will notice the Skill Senior / Lead Claim Processing Technician is not counted now.
- Anonymous3 years agoNot applicable
tamerj1 checking to see if you saw my response.