Driving activity

Hello Power Bi Experts,

I have a dataset as shown below, where an activity "F" has some relationships with 5 activities (A - E).

 

1. Activity A has FS (Finish to Start) relationship with Activity "F" with 10 days of Lag, meaning Activity F can only start 10 working days after Activity A finishes.

2. Activity B has FS (Finish to Start) relationship with Activity "F" with -10 days of Lag, meaning Activity F can only start 10 working days prior to Activity A finishes.

Similarly, when it comes to SS (Start to Start) as a connection (relationship) type, Activity A starts at the same time as the related activity starts with "Lag" either a positive or a negative value. The same goes with FF (Finish to Finish)  as a connection (relationship) type, Activity A finishes at the same time as the related activity finishes with "Lag" either a positive or a negative value.

 

 

 

 

The sample dataset above shows activity C is driving activity F to start by 21-Aug-2019.

C starts on 7 Aug 2019, and F starts 10 working days later because of the relationship type plus the lag.

 

What I am trying to find is, out of the above 5 (A to E) activities, which one does drive activity F using DAX in power bi? The conditions that I want to run on DAX are 

a. Connection Type (for every type)

b. Lag (Working days, excl Saturdays, Sundays, and certain public holidays)

c.  Start or Finish date of activities A to E depending on their connection type to activity F

 

At present, I use the below as DAX in power bi;

 

 

But the "Lag" in the above DAX represents just the number of days, not the working days, including the other public holidays.

 

I would appreciate your help in this regard.

 

Regards,

 

John