manthonio
New Member

DAx

how can i write DAX to phase out budgeted amount for 12 month period comulatively 

3 REPLIES 3
manthonio
New Member

so i have a budgeted amount of 20,000 and i want phased it for 12 months. when i pull in my actual cost i can tell which month i am executing according to planned. 

 

thank you 

qqqqqwwwweeerrr
Super User
Super User

Hi @manthonio 

 

Could you please share your input data/or sample masked data along with the expected output?

 

Regards

so i have a budgeted amount of 20,000 and i want phased it for 12 months. when i pull in my actual cost i can tell which month i am executing according to planned. 

 

thank you 

Helpful resources

Announcements
Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

October Power BI Update Carousel

Power BI Monthly Update - October 2025

Check out the October 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.