Calculating Percentage time remaining

Hi

 

I am trying to create a Measure to work out a percentage of time remaining on a project, this takes into account todays date.  All the data in in a single table.  The table has many rows, the difference is they have a varied budgets amounts but they all share the same 'Code', and same 'Start' and 'End' date.  I can created a calculated columns hoping this would help but my calculation just throughs out odd amounts; I am sure its becase there is the same value for each code per row.  I cant groupby the table, this is my sample:

 

Sample Data

 

So I was aiming to create ameasure that when I select the code 'ABC' in a matrix or pivot, I just get "-1%", but it does some thing alltogether and seems to add up numerous values.  

 

I have tried formula like: SUMX('TableA', sum('TableA'[Remaining Days')/sum('TableA'[Project No Of Days]))

 

I alos attempted a separte measure for calculatign the "no of days" rather than a calculated column, but again odd results, sample forulmula like this: SUMX('TbaleA', sum('TableA'[End Date')-SUM('TableA'[Start Date]))

 

Is it something to do with 'Row Context' maybe?  There is no filter contect, that I know of.   What am I doing wrong, in theory its a simple calculation?

 

Chris

  • Fowmy's avatar
    Fowmy
    6 years ago

    Anonymous 

    You need two measures:

    Remaining Days = 
    
    INT(TODAY() - MAX(Project[End date]))
    % Remaining = 
    
    DIVIDE(
        [Remaining Days],
        MAX(Project[Project No of days])
    )

     

     

    ________________________

    Did I answer your question? Mark this post as a solution, this will help others!.

    Click on the Thumbs-Up icon if you like this reply 🙂

    YouTube, LinkedIn

     

5 Replies

  • Anonymous 

    What is your expected results ? Can you show it for  one code?

    Can you try this :

     

    m = 
    
    SUMX('TableA', 
    DIVIDE(
        'TableA'[Remaining Days],
        'TableA'[Project No of days])
    )
    
     

     



    ________________________

    Did I answer your question? Mark this post as a solution, this will help others!.

    Click on the Thumbs-Up icon if you like this reply 🙂

    YouTube, LinkedIn




    • Anonymous's avatar
      Anonymous
      Not applicable

      Hi Fowmy

       

      This is the results I get:

      codeStart DateEnd dateProject No of daysThis is what it should be  ::Remaining DaysThe resulst I want ::Time remaining %New Measure
      ABC05/09/201604/08/20201429-20-1%-5%
      ZZZ01/05/200831/12/2008244-4254-1743%-15752%
      AAA01/12/201930/11/20203659827%27%
      EFG01/07/201830/12/202091312814%127%

       

      The colums in Green is what I am tryign to acheive.

      The column in Blue is what I am am trying to acheive.

      The column in Red is the new measure, its getting there slowly.

       

      I made sure all the values come from the same table, trying to remove an filter context.  I may need to rethink my how I am doing calculations, these are based around todays date.

       

      Alos even though not inlustrated, onthe source tabel theerare several rows for ABC, ZZ etc, here I am just showing one line for simplicity.

       

      Project No of Days = start date-end date

      Remaining Days = End Date - Today()

      % Time Remaining Measure = Remaining Days / Project No of Days

       

      Chris

      • Fowmy's avatar
        Fowmy
        Icon for Super User rankSuper User

        Anonymous 

        You need two measures:

        Remaining Days = 
        
        INT(TODAY() - MAX(Project[End date]))
        % Remaining = 
        
        DIVIDE(
            [Remaining Days],
            MAX(Project[Project No of days])
        )

         

         

        ________________________

        Did I answer your question? Mark this post as a solution, this will help others!.

        Click on the Thumbs-Up icon if you like this reply 🙂

        YouTube, LinkedIn

         

  • Anonymous , Try like

    avergageX(summarize(Table, Table[code],Table[StartDate],Table[endDate],"_1", max(Table[project no of Days]), "_2",max(Table[remaining Days])), divide([_2],[_1]))