Backlog Measure

Hi All,

 

Could you help me with a backlog measure please, i wish to count all the Task ID's which have a date before today.

 

Columns - 

Task ID - 

Task Due Date

 

Thanks

1 ACCEPTED SOLUTION
johnt75
Super User
Super User

Backlog = CALCULATE( DISTINCTCOUNT( 'Table'[Task ID]), 'Table'[Task Due Date] < TODAY())

View solution in original post

2 REPLIES 2
Anonymous
Not applicable

Thank you for the fast reply! 

johnt75
Super User
Super User

Backlog = CALCULATE( DISTINCTCOUNT( 'Table'[Task ID]), 'Table'[Task Due Date] < TODAY())

Helpful resources

Announcements
July 2024 Power BI Update

Power BI Monthly Update - July 2024

Check out the July 2024 Power BI update to learn about new features.

July Newsletter

Fabric Community Update - July 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors