Average Days Between Inspections
Hi, I am trying to get the average days between inspection dates. Below is a breakdown of current dates by project (with blue and green dots being 2 different projects). Below is my attempted...
- 3 years ago
Anonymous
Please tryAverageDaysBetweenInspections = AVERAGEX ( SUMMARIZE ( 'HSE Inspection', Project[ProjectName], 'Date of Inspection'[date] ), VAR CurrentDate = 'Date of Inspection'[date] VAR CurrentProjectTable = CALCULATETABLE ( SUMMARIZE ( 'HSE Inspection', Project[ProjectName], 'Date of Inspection'[date] ), ALL ( 'Date of Inspection'[date] ) ) VAR TableBefore = FILTER ( CurrentProjectTable, 'Date of Inspection'[date] < CurrentDate ) VAR PreviousDate = MAXX ( TableBefore, 'Date of Inspection'[date] ) RETURN IF ( NOT ISEMPTY ( TableBefore ), INT ( CurrentDate - PreviousDate ) ) )
tamerj1
3 years agoCommunity Champion
Anonymous
You may try
AverageDaysBtweenInspectionAndToday =
AVERAGEX (
VALUES ( Project[ProjectName] ),
INT (
TODAY ()
- CALCULATE (
MAX ( 'Date of Inspection'[date] ),
CROSSFILTER ( 'HSE Inspection'[DateHSEInspectionCreatedOnInteger], 'Date of Inspection'[DateAsInteger], BOTH )
)
)
)
Anonymous
3 years agoNot applicable
tamerj1 ,
Amazing, thank you so much