Hi , i am using gantt 2.2.3 visualisation to show progress of projects. I want to show legend colour based on project status , but when i am adding the field in legend the % completion is changing to 100% which is incorrect.
45 % is the correct progress.
After adding the legend it is changing to 100%.
unfortunately i don't know the answer -
but i need to ask how you are formating your source data field? i cannot get %complete to work defined a decimal or percentage.
https://github.com/microsoft/powerbi-visuals-gantt/issues/229