End Date incorrect on Gantt chart 3.0.12.0

In 'Transform data' my dates are Start Date (01/25/2024 13:00 or 1:00PM) and End date (01/26/24 11:00 or 11:00AM)

KZumbach_1-1729267133172.png

 

WV End Date Actual is a hard date written in the source while the All End date is calculating within PowerBI the start date plus the duration. Both are getting the same results of (01/26/24 11:00 or 11:00AM)


however, in the Gantt chart the End Date is (01/26/2024 13:00 or 1:00PM) 

KZumbach_0-1729267089937.png

This is how I have the Visualizations sets up

KZumbach_2-1729267326757.png


How do I get the chart to provide the correct end date?

0 REPLIES 0

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.