Display Cumulative Percentage Over Time - Line Chart

I have a list of SAP Notifications.

Each Notification eventually gets a Work Order assigned to it as the job is planned.

And I have a date column for when the Work Order is created

Eventually every Notification will have a Work Order.

 

I want to show a Line Chart that tracks WO creation over time.  With time as the X-Axis and Percent Complete (Count of Work Orders/Count of Notifications) as the Y-Axis

So I can track the cumulative progress of WO creation from 0% to 100% over time

 

I haven't been able to incorporate time into any of the measures that I have tried

Any help would be appreciated

 

   

 

 

  • bgierwi2 OK, well, this is going to depend a bit on what date you use for your x-axis and whether you want to count all Notifications every time or just those that were created prior to the specific date on the axis. Making some simplifying assumptions and using the only date in your sample data it should look something like this:

    Measure =
      VAR __Date = MAX('Table'[Date Work Order Created])
      VAR __AllCount = COUNTROWS(ALL('Table'))
      VAR __CurrentCount = COUNTROWS(FILTER(ALL('Table'),[Date Work Order Created] <> BLANK() && [Date Work Order Created] <= __Date))
    RETURN
      DIVIDE(__CurrentCount, __AllCount, 0)

4 Replies

  • Greg_Deckler's avatar
    Greg_Deckler
    Community Champion

    bgierwi2 Maybe this? 
    Take a look at these two Quick Measures as I think you want something like them.
    https://community.powerbi.com/t5/Quick-Measures-Gallery/Open-Tickets/m-p/409364
    https://community.powerbi.com/t5/Quick-Measures-Gallery/Periodic-Billing/m-p/409365

     

    If not, Sorry, having trouble following, can you post sample data as text and expected output?
    Not really enough information to go on, please first check if your issue is a common issue listed here: https://community.powerbi.com/t5/Community-Blog/Before-You-Post-Read-This/ba-p/1116882

    Also, please see this post regarding How to Get Your Question Answered Quickly: https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490

    The most important parts are:
    1. Sample data as text, use the table tool in the editing bar
    2. Expected output from sample data
    3. Explanation in words of how to get from 1. to 2.

    • bgierwi2's avatar
      bgierwi2
      Advocate I

      Greg_Deckler - Thank your for the response:

       

      Here is some sample data

      All of the notifications are already generated, and planners are creating WOs as they plan the work.

      As a Work Order is created, another column shows the date the Work Order is created

      This is in progress, eventually every notifiication will have a Work Order, and the progress will be 100%

       

      NotificationWork OrderDate Work Order Created
      17460816906961049/9/2022
      17452563  
      17452566930727629/1/2022
      17452680  
      17452682951132388/15/2022
      17452566  
      17451599951155728/14/2022
      17451601  
      17451602  
      17451604993513748/1/2022

       

      I would like to have a line chart:

      X-Axis showing Date

      Y-Axis Showing Count (Work Orders) / Count (Notifications)

      That will track the progress of generating Work Orders from 0% to 100%

      With this sample data, the progress should start at 0% and end at 50% (5 Work Orders generated out of 10 Notifications), between 8/1/2022 and 9/9/2022

       

      I would like it to look something like what is below

       

       

       

      • Greg_Deckler's avatar
        Greg_Deckler
        Community Champion

        bgierwi2 OK, well, this is going to depend a bit on what date you use for your x-axis and whether you want to count all Notifications every time or just those that were created prior to the specific date on the axis. Making some simplifying assumptions and using the only date in your sample data it should look something like this:

        Measure =
          VAR __Date = MAX('Table'[Date Work Order Created])
          VAR __AllCount = COUNTROWS(ALL('Table'))
          VAR __CurrentCount = COUNTROWS(FILTER(ALL('Table'),[Date Work Order Created] <> BLANK() && [Date Work Order Created] <= __Date))
        RETURN
          DIVIDE(__CurrentCount, __AllCount, 0)