Forum Discussion
Anonymous
7 years agoNot applicable
As Timeline x-axis help
I have been using (successfully) the custom visual "As Timeline" to represent start/stop intervals on a non-time based measurement (measuring a task from start to stop, every day, based on non-sequen...
v-evelk
7 years agoMicrosoft Employee
I am not sure that I clearly understand your issue but it looks like Gantt chart may be suitable for your aim.
There are two such visuals in the store:
Kind Regards,
Evgenii Elkin,
Software Engineer
Microsoft Power BI Custom Visuals
[email protected]
Anonymous
7 years agoNot applicable
A Gantt chart won't work, because on a certain task (one band), it will only show one start & one end. The kind of visualization I'm using/looking for will allow daily logs of start/stop (based on location) and group those together in one band, showing gaps. So if a task was done from MP1 to MP5 on day one and on day two it was MP6 to MP8, then the band would show a gap from MP5 to MP6.