    <title>topic Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value in DAX Commands and Tips</title>
    <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4706730#M180263</link>
    <description>&lt;P&gt;This error shows up because you're trying to use a table (like what TOPN returns) where Power BI is expecting just one value—like when you're combining text or checking a condition.&lt;/P&gt;&lt;P&gt;You've already used MAXX(...) to get the task name and finish date from the filtered table. So instead of using LastCompletedTask (which is still a table), you should use the variable that holds the actual task name.&lt;BR /&gt;Just update this line:&lt;BR /&gt;&lt;EM&gt;LastCompletedTask &amp;amp; " finished on time"&lt;/EM&gt;&lt;BR /&gt;&lt;SPAN&gt;to&lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;EM&gt;BaselineCompletedTask &amp;amp; " finished on time"&lt;/EM&gt;&lt;/P&gt;&lt;P&gt;&lt;STRONG&gt;The corrected DAX formula:&lt;BR /&gt;&lt;/STRONG&gt;&lt;/P&gt;&lt;LI-CODE lang="markup"&gt;FirstLateMilestoneTask =
VAR TodayDate = TODAY()

-- Tasks that are late
VAR LateTasks =
    FILTER (
        msdyn_projecttask,
        msdyn_projecttask[Schedule Status] = "Off Schedule"
            &amp;amp;&amp;amp; msdyn_projecttask[Required Tasks.Flag] = "y"
            &amp;amp;&amp;amp; msdyn_projecttask[% Complete] &amp;lt; 1
            &amp;amp;&amp;amp; NOT ISBLANK ( msdyn_projecttask[Baseline Finish] )
    )
VAR FirstLateTask =
    TOPN ( 1, LateTasks, msdyn_projecttask[Baseline Finish], ASC )
VAR TaskName =
    MAXX ( FirstLateTask, msdyn_projecttask[Project Task Name] )
VAR FinishDate =
    MAXX ( FirstLateTask, msdyn_projecttask[Finish] )
VAR FinishDaysLate =
    DATEDIFF ( FinishDate, TodayDate, DAY )

-- Tasks that are done
VAR CompletedTasks =
    FILTER (
        msdyn_projecttask,
        msdyn_projecttask[Schedule Status] &amp;lt;&amp;gt; "Off Schedule"
            &amp;amp;&amp;amp; msdyn_projecttask[Required Tasks.Flag] = "y"
            &amp;amp;&amp;amp; msdyn_projecttask[% Complete] = 1
            &amp;amp;&amp;amp; NOT ISBLANK ( msdyn_projecttask[Baseline Finish] )
    )
VAR LastCompletedTask =
    TOPN ( 1, CompletedTasks, msdyn_projecttask[Finish], DESC )
VAR BaselineCompletedTask =
    MAXX ( LastCompletedTask, msdyn_projecttask[Project Task Name] )
VAR BaselineFinishDate =
    MAXX ( LastCompletedTask, msdyn_projecttask[Baseline Finish] )
VAR ActualFinishDate =
    MAXX ( LastCompletedTask, msdyn_projecttask[Finish] )
VAR BaselineFinishDaysLate =
    DATEDIFF ( BaselineFinishDate, ActualFinishDate, DAY )

RETURN
    SWITCH (
        TRUE (),
        NOT ISBLANK ( TaskName ),
            TaskName &amp;amp; " is " &amp;amp; FinishDaysLate &amp;amp; " days past the expected completion date",
        BaselineFinishDaysLate = 0,
            BaselineCompletedTask &amp;amp; " finished on time",
        BLANK()
    )&lt;/LI-CODE&gt;&lt;P&gt;Let me know if you're pulling data from other related tables, or if you're using slicers in your report—I'm happy to help fine-tune it!&lt;/P&gt;&lt;P&gt;Feel free to share if it worked for you!&lt;/P&gt;&lt;P&gt;If it solves your issue, feel free to mark it as the accepted solution so others can benefit as well. And if you found it helpful, a thumbs-up is always appreciated!&lt;/P&gt;</description>
    <pubDate>Mon, 26 May 2025 06:04:03 GMT</pubDate>
    <dc:creator>Ilgar_Zarbali</dc:creator>
    <dc:date>2025-05-26T06:04:03Z</dc:date>
    <item>
      <title>The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4705516#M180221</link>
      <description>&lt;P&gt;I am trying to identify&lt;/P&gt;&lt;P&gt;1. for &amp;lt; than 100% complete milestones, it needs to return the first late milestone task by finish date and a status string indicating which task is late and by how many days.&lt;/P&gt;&lt;P&gt;2. for =100% complete, it needs to return the last milestone and say "finished on time"&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;DAX below gives error: "The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value".&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;FirstLateMilestoneTask =&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;TodayDate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;TODAY&lt;/SPAN&gt;&lt;SPAN&gt;()&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;( &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Schedule Status]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"Off Schedule"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Required Tasks.Flag]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"y"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[% Complete]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;lt; &lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)))&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;TOPN&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;, &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;ASC&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Project Task Name]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FinishDate&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;DATEDIFF&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FinishDate&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;SPAN&gt;TODAY&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;SPAN&gt;DAY&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;BR /&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;CompletedTasks&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;( &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;, &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Schedule Status]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;lt;&amp;gt; &lt;/SPAN&gt;&lt;SPAN&gt;"Off Schedule"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Required Tasks.Flag]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"y"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[% Complete]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp;&amp;nbsp;&lt;/SPAN&gt;&lt;/FONT&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp;&amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)))&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;LastCompletedTask&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;TOPN&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;CompletedTasks&lt;/SPAN&gt;&lt;SPAN&gt;, &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Finish]&lt;/SPAN&gt;&lt;SPAN&gt;, &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;DESC&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;BaselineCompletedTask&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;LastCompletedTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Project Task Name]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;BaselineFinishDate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;LastCompletedTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;BaselineFinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;DATEDIFF&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;BaselineFinishDate&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;MAX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Finish]&lt;/SPAN&gt;&lt;SPAN&gt;),&lt;/SPAN&gt;&lt;SPAN&gt;DAY&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;BR /&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;RETURN&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;SWITCH&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;TRUE&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt; &lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt;),&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" is "&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;FinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" days past the expected completion date"&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;BLANK&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;BaselineFinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;0&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;LastCompletedTask&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" finished on time"&lt;/SPAN&gt;&lt;/FONT&gt;&lt;FONT size="2"&gt;&lt;SPAN&gt;&amp;nbsp; )&lt;/SPAN&gt;&lt;/FONT&gt;&lt;/DIV&gt;&lt;/DIV&gt;</description>
      <pubDate>Fri, 23 May 2025 17:48:21 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4705516#M180221</guid>
      <dc:creator>PC2022</dc:creator>
      <dc:date>2025-05-23T17:48:21Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4705582#M180222</link>
      <description>&lt;P&gt;Hi&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="403139" data-lia-user-login="PC2022" class="lia-mention lia-mention-user"&gt;PC2022&lt;/a&gt;&amp;nbsp;please share the sample of your data model or pbix file?&lt;/P&gt;</description>
      <pubDate>Fri, 23 May 2025 19:59:34 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4705582#M180222</guid>
      <dc:creator>techies</dc:creator>
      <dc:date>2025-05-23T19:59:34Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4706730#M180263</link>
      <description>&lt;P&gt;This error shows up because you're trying to use a table (like what TOPN returns) where Power BI is expecting just one value—like when you're combining text or checking a condition.&lt;/P&gt;&lt;P&gt;You've already used MAXX(...) to get the task name and finish date from the filtered table. So instead of using LastCompletedTask (which is still a table), you should use the variable that holds the actual task name.&lt;BR /&gt;Just update this line:&lt;BR /&gt;&lt;EM&gt;LastCompletedTask &amp;amp; " finished on time"&lt;/EM&gt;&lt;BR /&gt;&lt;SPAN&gt;to&lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;EM&gt;BaselineCompletedTask &amp;amp; " finished on time"&lt;/EM&gt;&lt;/P&gt;&lt;P&gt;&lt;STRONG&gt;The corrected DAX formula:&lt;BR /&gt;&lt;/STRONG&gt;&lt;/P&gt;&lt;LI-CODE lang="markup"&gt;FirstLateMilestoneTask =
VAR TodayDate = TODAY()

-- Tasks that are late
VAR LateTasks =
    FILTER (
        msdyn_projecttask,
        msdyn_projecttask[Schedule Status] = "Off Schedule"
            &amp;amp;&amp;amp; msdyn_projecttask[Required Tasks.Flag] = "y"
            &amp;amp;&amp;amp; msdyn_projecttask[% Complete] &amp;lt; 1
            &amp;amp;&amp;amp; NOT ISBLANK ( msdyn_projecttask[Baseline Finish] )
    )
VAR FirstLateTask =
    TOPN ( 1, LateTasks, msdyn_projecttask[Baseline Finish], ASC )
VAR TaskName =
    MAXX ( FirstLateTask, msdyn_projecttask[Project Task Name] )
VAR FinishDate =
    MAXX ( FirstLateTask, msdyn_projecttask[Finish] )
VAR FinishDaysLate =
    DATEDIFF ( FinishDate, TodayDate, DAY )

-- Tasks that are done
VAR CompletedTasks =
    FILTER (
        msdyn_projecttask,
        msdyn_projecttask[Schedule Status] &amp;lt;&amp;gt; "Off Schedule"
            &amp;amp;&amp;amp; msdyn_projecttask[Required Tasks.Flag] = "y"
            &amp;amp;&amp;amp; msdyn_projecttask[% Complete] = 1
            &amp;amp;&amp;amp; NOT ISBLANK ( msdyn_projecttask[Baseline Finish] )
    )
VAR LastCompletedTask =
    TOPN ( 1, CompletedTasks, msdyn_projecttask[Finish], DESC )
VAR BaselineCompletedTask =
    MAXX ( LastCompletedTask, msdyn_projecttask[Project Task Name] )
VAR BaselineFinishDate =
    MAXX ( LastCompletedTask, msdyn_projecttask[Baseline Finish] )
VAR ActualFinishDate =
    MAXX ( LastCompletedTask, msdyn_projecttask[Finish] )
VAR BaselineFinishDaysLate =
    DATEDIFF ( BaselineFinishDate, ActualFinishDate, DAY )

RETURN
    SWITCH (
        TRUE (),
        NOT ISBLANK ( TaskName ),
            TaskName &amp;amp; " is " &amp;amp; FinishDaysLate &amp;amp; " days past the expected completion date",
        BaselineFinishDaysLate = 0,
            BaselineCompletedTask &amp;amp; " finished on time",
        BLANK()
    )&lt;/LI-CODE&gt;&lt;P&gt;Let me know if you're pulling data from other related tables, or if you're using slicers in your report—I'm happy to help fine-tune it!&lt;/P&gt;&lt;P&gt;Feel free to share if it worked for you!&lt;/P&gt;&lt;P&gt;If it solves your issue, feel free to mark it as the accepted solution so others can benefit as well. And if you found it helpful, a thumbs-up is always appreciated!&lt;/P&gt;</description>
      <pubDate>Mon, 26 May 2025 06:04:03 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4706730#M180263</guid>
      <dc:creator>Ilgar_Zarbali</dc:creator>
      <dc:date>2025-05-26T06:04:03Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4706833#M180268</link>
      <description>&lt;P&gt;Hi&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="403139" data-lia-user-login="PC2022" class="lia-mention lia-mention-user"&gt;PC2022&lt;/a&gt;&amp;nbsp;,&lt;/P&gt;
&lt;P&gt;Thank you for reaching out to Microsoft Fabric Community.&lt;/P&gt;
&lt;P&gt;&lt;SPAN&gt;Thank you&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="645372" data-lia-user-login="techies" class="lia-mention lia-mention-user"&gt;techies&lt;/a&gt;&amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;for the prompt response.&lt;/SPAN&gt;&lt;/P&gt;
&lt;P&gt;Yes - the error you're getting (&lt;SPAN&gt;"The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value".&lt;/SPAN&gt;) comes from this part:&lt;/P&gt;
&lt;P&gt;LastCompletedTask &amp;amp; " finished on time"&lt;BR /&gt;LastCompletedTask is a table (result of TOPN), and you're trying to concatenate it with text, which requires a scalar value.&lt;/P&gt;
&lt;P&gt;I have created a measure called "&lt;SPAN&gt;FirstLateMilestoneTask" in the attached pbix file which can solve the issue, please go through it.&lt;/SPAN&gt;&lt;/P&gt;
&lt;DIV&gt;&amp;nbsp;&lt;/DIV&gt;
&lt;P&gt;If this post&amp;nbsp;helps, then please consider&amp;nbsp;Accepting as solution&amp;nbsp;to help the other members find it more quickly,&amp;nbsp;don't forget to give a&amp;nbsp;"Kudos"&amp;nbsp;– I’d truly appreciate it!&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&lt;LI-WRAPPER&gt;&lt;SPAN data-teams="true"&gt;Thank you.&lt;/SPAN&gt;&lt;/LI-WRAPPER&gt;&lt;/P&gt;
&lt;P&gt;&lt;SPAN&gt; &lt;/SPAN&gt;&lt;/P&gt;
&lt;P&gt;&lt;LI-WRAPPER&gt;&lt;/LI-WRAPPER&gt;&lt;/P&gt;</description>
      <pubDate>Mon, 26 May 2025 06:43:45 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4706833#M180268</guid>
      <dc:creator>v-venuppu</dc:creator>
      <dc:date>2025-05-26T06:43:45Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4709447#M180358</link>
      <description>&lt;P&gt;Not working. I am trying to figure it out and will post once i do.&lt;/P&gt;</description>
      <pubDate>Tue, 27 May 2025 19:54:58 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4709447#M180358</guid>
      <dc:creator>PC2022</dc:creator>
      <dc:date>2025-05-27T19:54:58Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4709448#M180359</link>
      <description>&lt;P&gt;Not working. I am trying to figure it out and will post once i do.&lt;/P&gt;</description>
      <pubDate>Tue, 27 May 2025 19:55:14 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4709448#M180359</guid>
      <dc:creator>PC2022</dc:creator>
      <dc:date>2025-05-27T19:55:14Z</dc:date>
    </item>
    <item>
      <title>Re: The expression refers to multiple columns. Multiple columns cannot be converted to a scalar value</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4710968#M180411</link>
      <description>&lt;P&gt;I had to separate the above DAX into 2 measures. One for Late Tasks, the other for completed ones. They both worked.&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;DIV&gt;&lt;DIV&gt;&lt;DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;FirstLateMilestoneTask =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;TodayDate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;TODAY&lt;/SPAN&gt;&lt;SPAN&gt;()&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;( &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Schedule Status]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"Off Schedule"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Required Tasks.Flag]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"y"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[% Complete]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;lt; &lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)))&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;TOPN&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Finish]&lt;/SPAN&gt;&lt;SPAN&gt;, &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;ASC&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Project Task Name]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FinishDate&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; = &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;DATEDIFF&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FinishDate&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;SPAN&gt;TODAY&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;SPAN&gt;DAY&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;BR /&gt;&lt;DIV&gt;&lt;SPAN&gt;RETURN&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;SWITCH&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;TRUE&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt; &lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt;),&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;TaskName&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" is "&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;FinishDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" days past the expected completion date"&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;BLANK&lt;/SPAN&gt;&lt;SPAN&gt;() &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; )&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&amp;nbsp;&lt;/DIV&gt;&lt;DIV&gt;&amp;nbsp;&lt;/DIV&gt;&lt;/DIV&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;CompletedTasks1 =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;TodayDate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;TODAY&lt;/SPAN&gt;&lt;SPAN&gt;()&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt; =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;( &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Schedule Status]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"Off Schedule"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp;&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Required Tasks.Flag]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;"y"&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp;&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[% Complete]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;lt; &lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp;&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;NOT&lt;/SPAN&gt; &lt;SPAN&gt;ISBLANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Finish]&lt;/SPAN&gt;&lt;SPAN&gt;) &amp;nbsp; &amp;nbsp;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;FirstLateStartTask&lt;/SPAN&gt;&lt;SPAN&gt; =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;TOPN&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;1&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;LateTasks&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Start]&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;ASC&lt;/SPAN&gt;&lt;SPAN&gt; &amp;nbsp; &amp;nbsp;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;BR /&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;StartTaskName&lt;/SPAN&gt;&lt;SPAN&gt; =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateStartTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Project Task Name]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;StartDate&lt;/SPAN&gt;&lt;SPAN&gt; =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;FirstLateStartTask&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;msdyn_projecttask&lt;/SPAN&gt;&lt;SPAN&gt;[Baseline Start]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;StartDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;DATEDIFF&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;StartDate&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;TodayDate&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;DAY&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;RETURN&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;SWITCH&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;TRUE&lt;/SPAN&gt;&lt;SPAN&gt;(),&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;StartDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; &amp;gt; &lt;/SPAN&gt;&lt;SPAN&gt;0&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;StartTaskName&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" is "&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;StartDaysLate&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;" days past the expected start date"&lt;/SPAN&gt;&lt;SPAN&gt;,&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp;&lt;/SPAN&gt;&lt;SPAN&gt;"All required tasks are on track."&lt;/SPAN&gt;&lt;SPAN&gt; &amp;nbsp; &amp;nbsp;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;/DIV&gt;</description>
      <pubDate>Wed, 28 May 2025 20:47:28 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/The-expression-refers-to-multiple-columns-Multiple-columns/m-p/4710968#M180411</guid>
      <dc:creator>PC2022</dc:creator>
      <dc:date>2025-05-28T20:47:28Z</dc:date>
    </item>
  </channel>
</rss>
