    <title>topic Determining the Completion Date Based on the Start Date + &amp;lt;xx&amp;gt; Working Days in DAX Commands and Tips</title>
    <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3801574#M148635</link>
    <description>&lt;P&gt;Hi,&amp;nbsp;&lt;BR /&gt;I am currently working with two specific tables: a Fact Table and a Calendar Table. My objective is to accurately calculate the completion date for each entry. The formula to determine the completion date is: Start Date + Number of Working Days.&lt;/P&gt;&lt;P&gt;&lt;BR /&gt;Fact Table&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;&lt;BR /&gt;Calender Table&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;For example, if the start date is 2017/01/01(1st Jan 2017), then the completion date should be 2017/01/06.&lt;BR /&gt;Similarly, for a start date of 2017/01/02, the completion date should be 2017/01/09&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;I seek guidance on how to implement this calculation effectively. Any assistance or advice you can provide would be greatly appreciated.&lt;/P&gt;&lt;P&gt;Thank you for your support.&lt;BR /&gt;&lt;BR /&gt;Best,&lt;BR /&gt;Rosh&lt;/P&gt;</description>
    <pubDate>Mon, 01 Apr 2024 07:56:04 GMT</pubDate>
    <dc:creator>Rosh88</dc:creator>
    <dc:date>2024-04-01T07:56:04Z</dc:date>
    <item>
      <title>Determining the Completion Date Based on the Start Date + &lt;xx&gt; Working Days</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3801574#M148635</link>
      <description>&lt;P&gt;Hi,&amp;nbsp;&lt;BR /&gt;I am currently working with two specific tables: a Fact Table and a Calendar Table. My objective is to accurately calculate the completion date for each entry. The formula to determine the completion date is: Start Date + Number of Working Days.&lt;/P&gt;&lt;P&gt;&lt;BR /&gt;Fact Table&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;&lt;BR /&gt;Calender Table&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;For example, if the start date is 2017/01/01(1st Jan 2017), then the completion date should be 2017/01/06.&lt;BR /&gt;Similarly, for a start date of 2017/01/02, the completion date should be 2017/01/09&lt;/P&gt;&lt;P&gt;&lt;img /&gt;&lt;/P&gt;&lt;P&gt;I seek guidance on how to implement this calculation effectively. Any assistance or advice you can provide would be greatly appreciated.&lt;/P&gt;&lt;P&gt;Thank you for your support.&lt;BR /&gt;&lt;BR /&gt;Best,&lt;BR /&gt;Rosh&lt;/P&gt;</description>
      <pubDate>Mon, 01 Apr 2024 07:56:04 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3801574#M148635</guid>
      <dc:creator>Rosh88</dc:creator>
      <dc:date>2024-04-01T07:56:04Z</dc:date>
    </item>
    <item>
      <title>Re: Determining the Completion Date Based on the Start Date + &lt;xx&gt; Working Days</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3801708#M148645</link>
      <description>&lt;P&gt;Hi&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="715626" data-lia-user-login="Rosh88" class="lia-mention lia-mention-user"&gt;Rosh88&lt;/a&gt;&amp;nbsp;calculation logic should include Item column as you want to know Comp.Date based on Item column also?&lt;/P&gt;</description>
      <pubDate>Mon, 01 Apr 2024 09:03:15 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3801708#M148645</guid>
      <dc:creator>some_bih</dc:creator>
      <dc:date>2024-04-01T09:03:15Z</dc:date>
    </item>
    <item>
      <title>Re: Determining the Completion Date Based on the Start Date + &lt;xx&gt; Working Days</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3802337#M148665</link>
      <description>&lt;P&gt;hi&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="715626" data-lia-user-login="Rosh88" class="lia-mention lia-mention-user"&gt;Rosh88&lt;/a&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;I have a disconnected CALENDAR Table, please note that I have True/False(Boolean) in IsWorkingDay, you can change DAX to &lt;SPAN&gt;'CALENDAR'&lt;/SPAN&gt;&lt;SPAN&gt;[IsWorkingDay] = 1 instead of just&amp;nbsp; 'CALENDAR'[IsWorkingDay]&lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;This is a calculated column&lt;/P&gt;&lt;DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;CompletionDate =&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;_StartDate&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;'Fact'&lt;/SPAN&gt;&lt;SPAN&gt;[StartDate]&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;_WorkingDays&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;'Fact'&lt;/SPAN&gt;&lt;SPAN&gt;[WorkingDays]&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;_FltrTable&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;'CALENDAR'&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;'CALENDAR'&lt;/SPAN&gt;&lt;SPAN&gt;[IsWorkingDay]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;amp;&amp;amp; &lt;/SPAN&gt;&lt;SPAN&gt;'CALENDAR'&lt;/SPAN&gt;&lt;SPAN&gt;[Date]&lt;/SPAN&gt;&lt;SPAN&gt; &amp;gt;= &lt;/SPAN&gt;&lt;SPAN&gt;_StartDate&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;VAR&lt;/SPAN&gt; &lt;SPAN&gt;_WorkingDaysTbl&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;ADDCOLUMNS&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;_FltrTable&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;"@RANK"&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; &lt;/SPAN&gt;&lt;SPAN&gt;RANK&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;DENSE&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;_FltrTable&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;ORDERBY&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;'CALENDAR'&lt;/SPAN&gt;&lt;SPAN&gt;[Date]&lt;/SPAN&gt;&lt;SPAN&gt;)) &lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&lt;SPAN&gt;&amp;nbsp; &amp;nbsp; &amp;nbsp; &amp;nbsp; )&lt;/SPAN&gt;&lt;/DIV&gt;&lt;BR /&gt;&lt;DIV&gt;&lt;SPAN&gt;RETURN&lt;/SPAN&gt; &lt;SPAN&gt;MAXX&lt;/SPAN&gt;&lt;SPAN&gt;( &lt;/SPAN&gt;&lt;SPAN&gt;FILTER&lt;/SPAN&gt;&lt;SPAN&gt;(&lt;/SPAN&gt;&lt;SPAN&gt;_WorkingDaysTbl&lt;/SPAN&gt;&lt;SPAN&gt;, &lt;/SPAN&gt;&lt;SPAN&gt;[@RANK]&lt;/SPAN&gt;&lt;SPAN&gt; = &lt;/SPAN&gt;&lt;SPAN&gt;_WorkingDays&lt;/SPAN&gt;&lt;SPAN&gt;), &lt;/SPAN&gt;&lt;SPAN&gt;[Date]&lt;/SPAN&gt;&lt;SPAN&gt;)&lt;/SPAN&gt;&lt;/DIV&gt;&lt;DIV&gt;&amp;nbsp;&lt;/DIV&gt;&lt;DIV&gt;&lt;img /&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;/DIV&gt;&lt;/DIV&gt;</description>
      <pubDate>Mon, 01 Apr 2024 12:29:12 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3802337#M148665</guid>
      <dc:creator>talespin</dc:creator>
      <dc:date>2024-04-01T12:29:12Z</dc:date>
    </item>
    <item>
      <title>Re: Determining the Completion Date Based on the Start Date + &lt;xx&gt; Working Days</title>
      <link>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3802541#M148672</link>
      <description>&lt;P&gt;Hi&amp;nbsp;&lt;a href="javascript:void(0)" data-lia-user-mentions="" data-lia-user-uid="715626" data-lia-user-login="Rosh88" class="lia-mention lia-mention-user"&gt;Rosh88&lt;/a&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;I came up with a solution adding a [WorkdayOffset] column to my Date table.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;First I added a [IsWeekday] calculated column to my Date table.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;LI-CODE lang="markup"&gt;IsWeekday = IF( WEEKDAY( [Date], 2 ) &amp;gt; 5, 0, 1 )&lt;/LI-CODE&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;Then I added my [WorkdayOffset] column to my Date table.&amp;nbsp; This is to keep track of workdays.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;LI-CODE lang="markup"&gt;WorkdayOffset = 
VAR _Curr = [Date]
VAR _Table =
    FILTER(
        SUMMARIZE(
            ALL( 'Date' ),
            'Date'[Date],
            'Date'[IsWeekday]
        ),
        'Date'[IsWeekday] = 1
    )
VAR _Min =
    IF(
        _Curr &amp;lt; TODAY(),
        _Curr,
		TODAY()
    )
VAR _Max =
    IF(
        _Curr &amp;lt; TODAY(),
        TODAY(),
		_Curr
    )
VAR _Count =
    COUNTROWS(
        FILTER(
            _Table,
            [Date] &amp;gt;= _Min
                &amp;amp;&amp;amp; [Date] &amp;lt;= _Max
        )
    ) - 1
VAR _Logic =
    IF(
        _Curr &amp;gt;= TODAY(),
        _Count,
        _Count * -1
    )
RETURN
    _Logic
&lt;/LI-CODE&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;Finally, I added a [Completion Date] calculated column to the main table.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;LI-CODE lang="markup"&gt;Completion Date = 
VAR _Start = [StartDate]
VAR _WorkDays = [WorkingDays]
VAR _StartOffset = 
    CALCULATE(
        MAX( 'Date'[WorkdayOffset] ),
        'Date'[Date] = _Start
    )
VAR _End =
    CALCULATE(
        MAX( 'Date'[Date] ),
        'Date'[WorkdayOffset] = _StartOffset + _WorkDays - 1
    )
RETURN
    _End&lt;/LI-CODE&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;Let me know if you have any questions.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&lt;A href="https://1drv.ms/u/s!AnF6rI36HAVkhYYirZiqFovMzbLqRQ?e=vpOkyg" target="_blank" rel="noopener"&gt;Completion Date.pbix&lt;/A&gt;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Wed, 10 Apr 2024 15:54:37 GMT</pubDate>
      <guid>https://community.fabric.microsoft.com/t5/DAX-Commands-and-Tips/Determining-the-Completion-Date-Based-on-the-Start-Date-lt-xx-gt/m-p/3802541#M148672</guid>
      <dc:creator>gmsamborn</dc:creator>
      <dc:date>2024-04-10T15:54:37Z</dc:date>