Calculate Date Durations between 2 dates

Good day,   i would like to calculate the duration between 2 dates, so my visual will be per stage and its duration 1. Do I create a calculated column for duration between the 2 dates? 2. then a ...
  • rajendraongole1's avatar
    1 year ago

    Hi icassiem - your suggested method of using a calculated column for individual durations and a calculated measure for aggregation is correct.

     

    using datediff. calculated column calculate duration days:

     

    Duration_Days =
    DATEDIFF(
    TableName[StartDate],
    TableName[EndDate],
    DAY
    )

    create a measure for total duration as 

    Total_Duration =
    SUM(TableName[Duration_Days])

     

    Convert Duration to Hours or Mixed Format

    Duration_Format =
    VAR Days = INT(TableName[Duration_Hours] / 24)
    VAR Hours = MOD(TableName[Duration_Hours], 24)
    RETURN
    Days & " days " & Hours & " hours"

     

    In your visual e.g., a table or matrix, add the "Stage" field to the rows.Add the Total_Duration measure to display the summed duration per stage.