Forum Discussion

kaushik_asv's avatar
kaushik_asv
Frequent Visitor
5 years ago
Solved

Dates - Shift times

Hello all, 

 

We run 2 shifts each day. Blue shift from 6.00 AM - 4.59 PM and Red shift runs from 5.00 PM - 3.59 AM. 

Looking to make a bar graph with Daily output on Y-axis on and Date field on X axis with shift as a legend.

I ran into a problem here. Ideally the data for Aug 31 is showing Blue shift without issues. Red shift crosses over between 2 dates. issue here is, I only see a small part of red shift data for that day. The rest of that data is carried over to September 1st. Also, for Aug 31, I will be seeing data from red shift of Aug 30th. 

 

Is there a way I could create a column to reflect the correct totals?

 

Thanks in advance.

1 Reply