Time Projection Modeling
- Anonymous2 years ago
Hi crobinson661 ,
Firstly, I think we need to create an unrelated DimStep table.
DimStep = VALUES('Time'[Step])I suggest you to try code as below to create a measure.
Projected Date = VAR _ITEM = MAX('Item'[Item]) VAR _Cost = SUM('Item'[Cost]) VAR _STEP = MAX(DimStep[Step]) VAR _STARTSTEP = MAX('Item'[Step]) VAR _UNDAYS = CALCULATE(SUM('Time'[Days]),FILTER(ALLSELECTED('Time'),'Time'[Cost Min]<=_Cost && 'Time'[Cost Max]>=_Cost && 'Time'[Step]>=_STARTSTEP &&'Time'[Step] <= _STEP)) VAR _TODAY = TODAY() /*This should be TODAY(), here we use 2024.06/07 to have a test.*/ RETURN IF(_ITEM<>BLANK()&&_STEP>=_STARTSTEP,_TODAY+_UNDAYS)Result is as below.
Best Regards,
Rico ZhouIf this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
what is your definition of "days"? How about weekends and holidays? Does your source data have actual starting dates?
I was going to use NETWORKINGDAYS to exclude weekends and in the output examples table above in the [Projected Date Explained] column I demonstrate that the number of NETWORKINGDAYS for each remaining step would be calculated off TODAY().
- Anonymous2 years agoNot applicable
Hi crobinson661 ,
Firstly, I think we need to create an unrelated DimStep table.
DimStep = VALUES('Time'[Step])I suggest you to try code as below to create a measure.
Projected Date = VAR _ITEM = MAX('Item'[Item]) VAR _Cost = SUM('Item'[Cost]) VAR _STEP = MAX(DimStep[Step]) VAR _STARTSTEP = MAX('Item'[Step]) VAR _UNDAYS = CALCULATE(SUM('Time'[Days]),FILTER(ALLSELECTED('Time'),'Time'[Cost Min]<=_Cost && 'Time'[Cost Max]>=_Cost && 'Time'[Step]>=_STARTSTEP &&'Time'[Step] <= _STEP)) VAR _TODAY = TODAY() /*This should be TODAY(), here we use 2024.06/07 to have a test.*/ RETURN IF(_ITEM<>BLANK()&&_STEP>=_STARTSTEP,_TODAY+_UNDAYS)Result is as below.
Best Regards,
Rico ZhouIf this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
- crobinson6612 years agoFrequent Visitor
Sorry for the delay in reply - Thanks for the assistance!!
I'm finding that this is giving me the resulting estimated completion date of the current [Step] but if there are multiple remaining [Step]s, it is not giving the estimated date of each of those as well. (See Return When Item A and B above)