Setting a field to null based on another field's value

Hey Everyone,   Background: I'm pulling team sprint data from Jira cloud and want to show what stories the team completed within a sprint. This is easy to do when a story is completed within a sin...
  • v-yulgu-msft's avatar
    7 years ago

    Hi Anonymous,

     

    You can add a calculated column.

    Completeed Date2 =
    IF (
        TB3[Sprint] = CALCULATE ( MAX ( TB3[Sprint] ), ALLEXCEPT ( TB3, TB3[Story] ) ),
        TB3[Completed Date],
        BLANK ()
    )

     