Hi all,

 

As a relatively new BI user, i've been able to find numerous solutions already using this forum, so thanks for your continuous contributions :).

 

New i'm running into a knowledge issue on my behalf, hoping someone has the magic tip ;-).

 

What i'm trying to accomplish:

Prediction of stock level next month.

 

What data I have

Stock level table (monthly dump)

Sales table

purchase orders table

turnover table (one for planned turnover, one for billed turnover)

work in progress table

 

Idea is to have:

Sum of stock level for in current month

+

sum of work in progress in current month

+

sum of purchase orders expected in current month

 

-

sum of planned sales in current month

-

sum of billed sales in current month

 

All tables are linked via general date table (marked as a date table). so far this work perfectly when laying out all the values next to each other.

 

Unfortunately I cant share the data as it's confidential information.

 

Thanks in advance for your help!

  • hi, PaulusD 

    For your data model, if these five tables are all linked with date table,

    If so just drag a year month column from date table and then create a measure 

    measure= Sum of stock level +sum of work in progress +sum of purchase orders expected - sum of planned sales 

    - sum of billed sales

    For conditional ( in current month),  you could add a calculate column to judge if this month is  in current month.

    then use if as a slicer.

    If not your case, please use virtual data to create a simple pbix file and share it with expected output for us.

    Please see this post regarding How to Get Your Question Answered Quickly: https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490

     

    Best Regards,

    Lin

     

     

4 Replies

  • v-lili6-msft's avatar
    v-lili6-msft
    Community Support

    hi, PaulusD 

    For your data model, if these five tables are all linked with date table,

    If so just drag a year month column from date table and then create a measure 

    measure= Sum of stock level +sum of work in progress +sum of purchase orders expected - sum of planned sales 

    - sum of billed sales

    For conditional ( in current month),  you could add a calculate column to judge if this month is  in current month.

    then use if as a slicer.

    If not your case, please use virtual data to create a simple pbix file and share it with expected output for us.

    Please see this post regarding How to Get Your Question Answered Quickly: https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490

     

    Best Regards,

    Lin

     

     

    • PaulusD's avatar
      PaulusD
      Resolver II

      Hi v-lili6-msft , thanks for your reply.

       

      I did't realize it would be that easy!

      I indeed added a calculate to test if the measue is in the current month and that seems to work fine.

       

      Now for the magic;

      What would really make this great is predicting stock levels for the coming +-6 months (per month)

      Do i need to create new measure for each time frame? (so for month +1, month +2, month +3 etc.)

       

      I would use the predicted stock for month +1, add:

      work in progress for month +1

      Purchase orders for month +1

      and subtract

      sales month +1

       

      and that should predict the stock levels for month +2.

       

      So would I need to repeat this say 5/6times? or could i manage this dynamically by saying show the above for the coming 6 months?

       

      Thanks again :)

      • v-lili6-msft's avatar
        v-lili6-msft
        Community Support

        hi, PaulusD 

        You do not need to repeat this say 5/6times, just keep the date table has the full date.

        For example:

        Yearmonth       Measure

        2019-01           100

        2019-02           150                Assume that this is the current month

        2019-03           200

        2019-04           150

        2019-05            120

        2019-06           100

        2019-07            90

        2019-08            80

         

        For the red part, As long as the date table has the full date, it will be calculated dynamically.

         

        Best Regards,

        Lin