Forum Discussion
Project.microsoft.com not PWA connection
Hello!
My company does not use PWA but we are trying to connect our Online Projects to a PowerBi report.
It is still looking for a PWA and I was wondering if anyone had any ideas on how to connect without using it.
- Anonymous3 years ago
Our fix was to release PWA sites. I found out we just never released the Sites in Sharepoints.
3 Replies
- amitchandak
Super User
Anonymous , not very clear what PWA?
The information you have provided is not making the problem clear to me. Can you please explain with an example.
Appreciate your Kudos.Anonymous
- AnonymousNot applicable
Many of the PowerBi templates have asked for the PWA URL. Our company uses the: https://project.microsoft.com/(company)/en-us
Using this connection type is not working for our dataset to import.
- AnonymousNot applicable
Our fix was to release PWA sites. I found out we just never released the Sites in Sharepoints.