PAS - Date Between Two Weeks
Hello. I have a series of activities that each have a start date and a finish date. I would like to set up a PAS (performance against schedule) with this data that will calculate the number of 'o...
Anonymous
3 years agoNot applicable
The results that I would like to achieve are the isolation of activities 4834, 9843, 9832 and 9821, a count of the total early and on time, a count of the total activities, and the PAS score resulting from those, which is count of early and on time over total as a percentage, PAS.
| Activity ID | Activity Name | Start 3 Weeks Ago | Start 2 Weeks Ago | Finish 3 Weeks Ago | Finish 2 Weeks Ago | Start Delta | Finish Delta | Start PAS | Finish PAS | Total On Time or Early | 7 | |
| 4834 | get permits | 3/6/2023 | 3/6/2023 | 3/7/2023 | 3/7/2023 | 0 | 0 | On Time | On Time | Total Activities | 8 | |
| 9843 | rough grade | 3/7/2023 | 3/7/2023 | 3/8/2023 | 3/8/2023 | 0 | 0 | On Time | On Time | PAS | 88% | |
| 9832 | grade | 3/8/2023 | 3/7/2023 | 3/9/2023 | 3/8/2023 | -1 | -1 | Early | Early | |||
| 9821 | compress | 3/9/2023 | 3/10/2023 | 3/10/2023 | 3/11/2023 | 1 | 1 | Late | Early | |||
| 9810 | frp | 3/13/2023 | 3/12/2023 | 3/14/2023 | 3/13/2023 | -1 | -1 | Early | Early | |||
| 9799 | cure | 3/14/2023 | 3/18/2023 | 3/15/2023 | 3/19/2023 | 4 | 4 | Late | Late | |||
| 9788 | frame | 3/18/2023 | 3/19/2023 | 3/19/2023 | 3/20/2023 | 1 | 1 | Late | Late | |||
| 9777 | drywall | 3/19/2023 | 3/20/2023 | 3/20/2023 | 3/21/2023 | 1 | 1 | Late | Late | |||
| 9766 | tfm | 3/20/2023 | 3/21/2023 | 3/21/2023 | 3/22/2023 | 1 | 1 | Late | Late | |||
| 9755 | electrical | 3/21/2023 | 3/22/2023 | 3/22/2023 | 3/23/2023 | 1 | 1 | Late | Late | |||
| 9744 | plumbing | 3/22/2023 | 3/25/2023 | 3/23/2023 | 3/26/2023 | 3 | 3 | Late | Late |