Hi kyleldi,
Firstly, create a calendar table in Power BI Desktop following the guide in this blog. Then create a column in the calendar table using the Dax below.is work day = SWITCH(WEEKDAY([Date]),1,0,7,0,1)
Secondly, create a measure using the following DAX and create a card visual.
Days= CALCULATE(SUM('Date'[is work day]), DATESBETWEEN('Date'[Date], [OldestDate], [NewestDate] ))Thanks,
Lydia Zhang
Maybe its old topic but easises solution is to create a custom function lik this:
(StartDate as date, EndDate as date) as number =>
let
DateList = List.Dates(StartDate, Number.FromText(EndDate-StartDate), #duration(1,0,0,0)),
RemoveWeekdns = List.Select(DateList, each Date.DayOfWeek(_, Day.Monday)<5),
CountDays = List.Count(RemoveWeekdns)
in
CountDays
And then just invoke it whenever needed.
They also just added NETWORKDAYS in DAX this month.
- Stephen_Sink4 years agoFrequent Visitor
Do I have to update my version of desktop to get this? im running 2.105
- newpowerbiuser83 years ago
Helper I
Hi,
I have this formula
Days with BSCM = IF('Sheet 1'[Send form to BSCM]="No","N/A",IF(ISBLANK('Sheet 1'[BOR updated date]),"",FORMAT(NETWORKDAYS('Sheet 1'[Form Submitted on],IF(ISBLANK('Sheet 1'[BOR updated date]),TODAY(),'Sheet 1'[BOR updated date]),1),"#")))Where it shows blank, I need to calculate days between Form Submitted on and TodayYour help will be really appreciated.