Milestone Burn Up/Down chart with % progress
Hi Community,
I would appreciate if any one could help me.
What I need:
- Line chart with two lines, one that shows the actual progress of milestone in % and one line showing planned progress from 0% to 100% (should be linear)
- Y-Axis: 0% to 100%, X-Axis: Milestone start date to due date
- The actual status line will be updated every two month with new % progress
What I have:
- Table with milestone data (start, due date)
- Table with Status of actual milestone progress in %
Here is the link to the BowerBI file incl. data base exampel and target picture of Burn Up chart: https://drive.google.com/file/d/1GkL957TFhi5dFriQVYA-FgP9X11nU-71/view?usp=sharing
I already read through similar cases here and watched videos, but I was not able to figure out a running solution for my case.
Thank you in advance and best regards,
Joh
Hi Anonymous ,
Just take "reporting date" as the X axis and add a trend line.
Best Regards,
Liang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
7 Replies
- V-lianl-msft
Community Support
Hi Anonymous ,
Based on your description, you can get the following results by using report date as x axis.
Best Regards,
Liang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.- AnonymousNot applicable
Hi V-lianl-msft ,
that looks very promising, thank you! Could you please share the pbi file from your solution, so that I can reproduce the graph?
Thanks and best,
Joh
- V-lianl-msft
Community Support
Hi Anonymous ,
Just take "reporting date" as the X axis and add a trend line.
Best Regards,
Liang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
- parry2k
Super User
Anonymous it will be easier if you throw a sample pbix file and share it thru one drive/google drive with the expected output and I'm sure someone will able to help you pretty quickly.
Check my latest blog post Compare Budgeted Scenarios vs. Actuals to get a summary of my favourite Power BI feature releases in 2020
I would ❤ Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos to whoever helped to solve your problem. It is a token of appreciation!
⚡Visit us at https://perytus.com, your one-stop-shop for Power BI-related projects/training/consultancy.⚡
- AnonymousNot applicable
Hi parry2k,
thanks for the hint, the file can be accessed via this link: https://drive.google.com/file/d/1GkL957TFhi5dFriQVYA-FgP9X11nU-71/view?usp=sharing
- parry2k
Super User
Anonymous I checked at the file, on x-axis, start to due, how the plan gets distributed over time?
- AnonymousNot applicable
Hi parry2k , yes, x-axis also needs to vary according start and due date of selected/filtered milestone. So it indicates the time of milestone start to planned milestone due date against the planned and actual progress on the y-axis.