Line Chart carrying out "SUM" function on values!

I have a line chart that has the below values...

 

Axis: Snapshotdate  {Date}

Legend: Project Name {Text}

Values: Completed (Decimal | Percentage | Dont Summarise)

 

The problem is the "Completed" values are being added together, where i want the individual completed percent values for each month showing, but it doesnt give me the option to "Dont Summerize" on the "Values" dropdown option.  I hope that makes sense.

 

 

 

 

 

  • StuartSmith let's assume the case here, if a project has two dates for the same month let's say 50% and then 99%, currently it is doing the sum of this ( correct? ), what would you like to see in this case 99% (I guess)

     

    so add a measure :

     

    Max % = MAX ( Table[Complete Percentage Column] )

     

    and use this measure in the value, basically, it will show the maximum complete % of a project if there are multiple entries of the same project in a month. I hope it helps.

     

    For date, on the formatting pane, under the x-axis choose continuous instead of categorical.

     

    ✨ Follow us on LinkedIn

     

    Learn about conditional formatting at Microsoft Reactor

    My latest blog post The Power of Using Calculation Groups with Inactive Relationships (Part 1) (perytus.com) I would ❤ Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos to whoever helped to solve your problem. It is a token of appreciation!

     

    ⚡ Visit us at https://perytus.com, your one-stop-shop for Power BI-related projects/training/consultancy.⚡

6 Replies

  • StuartSmith's avatar
    StuartSmith
    Icon for Power Participant rankPower Participant

    I have just found out that you can format a measure from the "Relationship" tab... 

     

    Anyway, thanks for your original measure fix, that started me on the path to a solution that I am happy with.

  • StuartSmith You cannot do that, you have to have an aggregation on the value section. Are you saying, you have projects with the same snapshot date with percentage?

    • StuartSmith's avatar
      StuartSmith
      Icon for Power Participant rankPower Participant

      Thanks for replying.  And yes, there will be multiple projects with the same "Snapshot Date" and varying % values.  I was just reading up on "Aggregates" on the link https://docs.microsoft.com/en-us/power-bi/create-reports/service-aggregates and at the bottom is says about if the data is from Excel and a calculated value.  The data is from an excel file, but not created via a formula.  

       

      I was just hoping to create a line chart of the progress of each project over the months. Here is an example of the data.  

       

      and I have also noticed if I select a data point, the "Month" is wrong (see below).

       

      How can I get it so it just show a line for each project and the monthly % value?  Thanks in advance.

  • StuartSmith let's assume the case here, if a project has two dates for the same month let's say 50% and then 99%, currently it is doing the sum of this ( correct? ), what would you like to see in this case 99% (I guess)

     

    so add a measure :

     

    Max % = MAX ( Table[Complete Percentage Column] )

     

    and use this measure in the value, basically, it will show the maximum complete % of a project if there are multiple entries of the same project in a month. I hope it helps.

     

    For date, on the formatting pane, under the x-axis choose continuous instead of categorical.

     

    ✨ Follow us on LinkedIn

     

    Learn about conditional formatting at Microsoft Reactor

    My latest blog post The Power of Using Calculation Groups with Inactive Relationships (Part 1) (perytus.com) I would ❤ Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos to whoever helped to solve your problem. It is a token of appreciation!

     

    ⚡ Visit us at https://perytus.com, your one-stop-shop for Power BI-related projects/training/consultancy.⚡

    • StuartSmith's avatar
      StuartSmith
      Icon for Power Participant rankPower Participant

      Thanks, and we are getting there.  I did change your code from "Max" to "Avg" as say if one country was on 100% completed and another on 50% completed, the line chart would give the impression that all countries where 100% completed, where as changing to Avg, it will give a Avg for all Countries.  Plus if only 1 country is selected, the values show correctly.

       

      I will test, but its looking good.  One thing I did nortice was that by adding the measure, its changed the formatting of the chart from 40% to 0.40 and the Axis range has gone from 0% > 100% to 0.0 > 1.0. Is there a way to format the measure output?

       

      Before

       

      After

       

      • StuartSmith's avatar
        StuartSmith
        Icon for Power Participant rankPower Participant

        I presumed...

        Avg % = FORMAT(AVERAGE(ProjectCompletionByCountry[Complete] ), "0.00%")
        would work, but the chart visual fails to display.