Hi,

I would like to add another condition to this IF Statement that says if the Created On date = Resolution Date then DAY+1

At the moment the Code is saying that when these dayes are the same then its 0 days which is wrong:

 

Case Length = 
IF (
    'Cases'[statecode] = "Active",
    DATEDIFF (
        IF (
            ISBLANK ( 'Cases'[legacycasecreationdate] ),
            'Cases'[Created On],
            'Cases'[legacycasecreationdate]
        ),
        NOW (),
        DAY
    ),
    DATEDIFF (
        IF (
            ISBLANK ( 'Cases'[legacycasecreationdate] ),
            'Cases'[Created On],
            'Cases'[legacycasecreationdate]
        ),
        'Cases'[Resolution Date],
        DAY
    )
)
  • Hi ArchStanton , try this formula.
    Logic Used:
    When the Created On equals the Resolution Date , return 1 day;
    otherwise for resolved cases return an inclusive day count (DATEDIFF + 1).
    For active cases the existing behaviour is preserved (you can switch to inclusive there too if you prefer).

    Case Length =
    VAR StartDate =
        IF(
            ISBLANK( 'Cases'[legacycasecreationdate] ),
            'Cases'[Created On],
            'Cases'[legacycasecreationdate]
        )
    VAR IsActive = 'Cases'[statecode] = "Active"
    VAR ResDate = 'Cases'[Resolution Date]
    RETURN
    IF(
        IsActive,
        -- Active: difference between StartDate and now (unchanged behaviour)
        DATEDIFF( StartDate, NOW(), DAY ),
        -- Resolved: handle blanks, same-day, otherwise inclusive DATEDIFF (+1)
        IF(
            ISBLANK( ResDate ),
            BLANK(),
            IF(
                DATEVALUE( StartDate ) = DATEVALUE( ResDate ),
                1,                                          -- same calendar day => 1
                DATEDIFF( StartDate, ResDate, DAY ) + 1    -- inclusive count
            )
        )
    )

    Notes / rationale

    • DATEVALUE(...) is used when comparing StartDate and ResDate so time components don’t make two same-day timestamps look different.

    • DATEDIFF(...)+1 gives an inclusive day count (e.g., start = 1-Jan, end = 2-Jan → 2 days).

    • If you want inclusive logic for active cases too, change the active branch to DATEDIFF( StartDate, NOW(), DAY ) + 1.

    • If you prefer to always return 0 rather than BLANK() for missing Resolution Date, replace BLANK() with 0.

    ⭐Hope this solution helps you make the most of Power BI! If it did, click 'Mark as Solution' to help others find the right answers.
    💡Found it helpful? Show some love with kudos 👍 as your support keeps our community thriving!
    🚀Let’s keep building smarter, data-driven solutions together!🚀 [Explore More]

5 Replies

  • Hi ArchStanton , try this formula.
    Logic Used:
    When the Created On equals the Resolution Date , return 1 day;
    otherwise for resolved cases return an inclusive day count (DATEDIFF + 1).
    For active cases the existing behaviour is preserved (you can switch to inclusive there too if you prefer).

    Case Length =
    VAR StartDate =
        IF(
            ISBLANK( 'Cases'[legacycasecreationdate] ),
            'Cases'[Created On],
            'Cases'[legacycasecreationdate]
        )
    VAR IsActive = 'Cases'[statecode] = "Active"
    VAR ResDate = 'Cases'[Resolution Date]
    RETURN
    IF(
        IsActive,
        -- Active: difference between StartDate and now (unchanged behaviour)
        DATEDIFF( StartDate, NOW(), DAY ),
        -- Resolved: handle blanks, same-day, otherwise inclusive DATEDIFF (+1)
        IF(
            ISBLANK( ResDate ),
            BLANK(),
            IF(
                DATEVALUE( StartDate ) = DATEVALUE( ResDate ),
                1,                                          -- same calendar day => 1
                DATEDIFF( StartDate, ResDate, DAY ) + 1    -- inclusive count
            )
        )
    )

    Notes / rationale

    • DATEVALUE(...) is used when comparing StartDate and ResDate so time components don’t make two same-day timestamps look different.

    • DATEDIFF(...)+1 gives an inclusive day count (e.g., start = 1-Jan, end = 2-Jan → 2 days).

    • If you want inclusive logic for active cases too, change the active branch to DATEDIFF( StartDate, NOW(), DAY ) + 1.

    • If you prefer to always return 0 rather than BLANK() for missing Resolution Date, replace BLANK() with 0.

    ⭐Hope this solution helps you make the most of Power BI! If it did, click 'Mark as Solution' to help others find the right answers.
    💡Found it helpful? Show some love with kudos 👍 as your support keeps our community thriving!
    🚀Let’s keep building smarter, data-driven solutions together!🚀 [Explore More]

  • Hi ArchStanton 

    Try this:

    -- Determine the "end date" depending on the case's state
    VAR _End =
        IF (
            'Cases'[statecode] = "Active",        -- If the case is still active,
            'Cases'[Resolution Date],             -- use its Resolution Date as end date,
            TODAY ()                              -- otherwise, use today's date or NOW() ?
        )
    
    -- Calculate the number of days between creation and end date
    VAR _DaysDiff =
        DATEDIFF (
            COALESCE (                             -- Use first available creation date:
                'Cases'[legacycasecreationdate],    -- Prefer legacy creation date if available,
                'Cases'[Created On]                 -- otherwise use the regular Created On date
            ),
            _End,                                  -- up to the end date determined above
            DAY                                    -- return the difference in days
        )
    
    -- Final return value:
    -- Add 1 day only if creation date equals resolution date; otherwise, return the normal difference
    RETURN
        IF (
            'Cases'[legacycasecreationdate] = 'Cases'[Resolution Date],
            _DaysDiff + 1,                         -- Same-day cases: count as 1 full day
            _DaysDiff                              -- Otherwise, just return the calculated difference
        )
    
  • ArchStanton 

     

    Case Length =
    VAR StartDate = IF(ISBLANK('Cases'[legacycasecreationdate]), 'Cases'[Created On], 'Cases'[legacycasecreationdate])
    VAR EndDate = IF('Cases'[statecode] = "Active", NOW(), 'Cases'[Resolution Date])
    VAR DaysDiff = DATEDIFF(StartDate, EndDate, DAY)
    RETURN
    IF(StartDate = EndDate, DaysDiff + 1, DaysDiff)

     

    If this answer helped, please click Kudos or mark as Solution.
    -Kedar
    LinkedIn: https://www.linkedin.com/in/kedar-pande

    • ArchStanton's avatar
      ArchStanton
      Icon for Power Participant rankPower Participant

      I've accepted another solution but I did try this and its not correct.

      An Active case is active so it cannot be resolved & have a resolution date

      I'm seeing cases with a created on = resolution date showing as 0 days when it should be 1

      A small amendment and it will work I think