Hi, could anyone help me with this problem..

 

I need to write formula witch takes filter value and used it in a formula. For example:

Filter of works: 

1. Work A

2. Work B

 

My formula should be: if (selected filter value is "work A", sum( all (table [random value])) * 0,7, if selected filter value is "work B", sum( all( table [random value])) * 0,3, blank () )

 

Thank a lot for the help!

  • Anonymous's avatar
    Anonymous
    6 years ago

    Hi Nathaniel_C,

    Thanks for your help, but this didn't work for me, because in "myTable[column]" I have wrong data from accounting program. That's why if I choose A or B work I need to split all costs by proportion of 0,7 and 0,3.

     

    I add my solution:

     

    work costs = if(SELECTEDVALUE('2019 details'[Work])="work A";CALCULATE(SUM('2019 details'[SUM])*0,7;all('2019 details [work]); if(SELECTEDVALUE('2019 details'[Work])="work B";CALCULATE(sum('2019 details'[SUM])*0,3;all('2019 details '[Work]); CALCULATE(sum('2019 details'[SUM]);all('2019 details '[Work])

     

     

     

3 Replies

  • Nathaniel_C's avatar
    Nathaniel_C
    Community Champion

    Hi Anonymous ,

    IF(myTable[column] = "work A", SUM(table[random value] *0,7,IF(myTable[column] = "work B", SUM(table[random value] *0,3)


    Let me know if you have any questions.

    If this solves your issues, please mark it as the solution, so that others can find it easily. Kudos 👍are nice too.
    Nathaniel 

    • Anonymous's avatar
      Anonymous
      Not applicable

      Hi Nathaniel_C,

      Thanks for your help, but this didn't work for me, because in "myTable[column]" I have wrong data from accounting program. That's why if I choose A or B work I need to split all costs by proportion of 0,7 and 0,3.

       

      I add my solution:

       

      work costs = if(SELECTEDVALUE('2019 details'[Work])="work A";CALCULATE(SUM('2019 details'[SUM])*0,7;all('2019 details [work]); if(SELECTEDVALUE('2019 details'[Work])="work B";CALCULATE(sum('2019 details'[SUM])*0,3;all('2019 details '[Work]); CALCULATE(sum('2019 details'[SUM]);all('2019 details '[Work])

       

       

       