Hi and thx for reading this.

I am not sure this will be able to do but i will try and see here ๐Ÿ™‚
I have a basic simple table:

 

 

 

 

 

 

 

 

I want to change the date (add 2 years to every row) and be able to put this new "Date" in an X axis for a Chart
I know that the simple way would to do this i a calculate column and do it the "normal way" but that is not what i want to do (since there will be a many of these date changes )

 

 

I want this "date change" in a measure and be able to use that measure in X -axis in a chart


Is this possible ?

Thx so much-

  • Hi Wresen 

     

    Measures themselves cannot be used as  dimensions as they don't have a filter context but they can be materialized using a column in a disconnected table which values are controlled by a measure. 

     

     

    Please see the attached sample pbix.  Otherwise,  please provide a workable sample data (not an image), your expected result from the same sample data and your reasoning behind. You may post a link to Excel or a sanitized copy of your PBIX stored in the cloud.

4 Replies

  • Hi Wresen 

     

    Measures themselves cannot be used as  dimensions as they don't have a filter context but they can be materialized using a column in a disconnected table which values are controlled by a measure. 

     

     

    Please see the attached sample pbix.  Otherwise,  please provide a workable sample data (not an image), your expected result from the same sample data and your reasoning behind. You may post a link to Excel or a sanitized copy of your PBIX stored in the cloud.

  • Wresen , A measure can not change axis. 

     

    But these measures will show data for previous or future date 

     

    2 years ahead = 

    Calculate([Net], dateadd(Date[Date],2, year))

     

    2 years behind 

    Calculate([Net], dateadd(Date[Date],-2, year))

     

    Assuming you have a date table joined your fact table 

     

    Why Time Intelligence Fails - Powerbi 5 Savior Steps for TI :https://youtu.be/OBf0rjpp5Hw
    https://amitchandak.medium.com/power-bi-5-key-points-to-make-time-intelligence-successful-bd52912a5bd4
    To get the best of the time intelligence function. Make sure you have a date calendar and it has been marked as the date in model view. Also, join it with the date column of your fact/s. Refer :radacad sqlbi My Video Series Appreciate your Kudos.

  • v-echaithra's avatar
    v-echaithra
    Icon for Community Support rankCommunity Support

    Hi Wresen ,

    Thank you for providing an update and confirming that the issue has been resolved. If you require any further assistance. Please feel free to let us know, weโ€™re happy to help!


    Thank you 
    Chaithra E.