Hi Team

 

If my RCC level is on R07 then my BW should start if it started showing 1, or not showing zero in another column

we need dax for the above querry

attaching excel with data

Case 1

 

 

 

9 Replies

  • not clear about your question 

    Could you pls explain more on this? or what's your excel formula?

    • sameergupta60's avatar
      sameergupta60
      Helper IV

      hi,

       

      My query is if my RCC level is on r07 then  my block work has to start date .

       

      but if my BW start date  is not started at any level then it is 0 or 1.

       

      for that, we need dax or measure.

       

      Regards,

      Sameer Gupta