Hi experts, below measure is giving wrong results in case of december month, please help YEAR - MONTH = IF ( DAY('CALENDAR'[Date]) > 25 , CONCATENATE( YEAR('CALENDAR'[Date]) & "-" , MONTH('CA...
Anonymous
4 years agoNot applicable
Sorry
This one should be ok
YEAR - MONTH =
IF ( DAY('CALENDAR'[Date]) > 25 && MONTH('CALENDAR'[Date])=12,
CONCATENATE( YEAR('CALENDAR'[Date])+1 & "-" , « 01 »),
IF ( DAY('CALENDAR'[Date]) > 25 ,
CONCATENATE( YEAR('CALENDAR'[Date]) & "-" , MONTH('CALENDAR'[Date])+1 ),
CONCATENATE( YEAR('CALENDAR'[Date]) & "-" , MONTH('CALENDAR'[Date])))