Good morning,

I have a table with a calendar, a column with the dates and a column with the number 1 for the days the company is open and 0 for the days the company is closed.

I have another table with a column with the start of production date and another with the end.

I need to datediff, filtering only the days the company is open, =1.

I can't understand how this dont work: 

Time Spent = CALCULATETABLE(datediff('Production'[Startdate],'Production'[Date Time],HOUR),FILTER(DateCalendar,DateCalendar[Workday]=1))

 

  • amitchandak's avatar
    amitchandak
    4 years ago

    Joao_C_Faria , id start date and end date are column in same table :Production, you can create a column in Production

     

    new column = countx(filter(DateCalendar, DateCalendar[Date] >= Production[Start Date] && DateCalendar[Date] <= Production[End Date] && DateCalendar[Workday]=1),DateCalendar[Date])

     

     

    else you have to take a measure approch

     

    How to calculate Business Days/ Workdays, with or without date table: https://youtu.be/Qv4wT8_P-AA

     

4 Replies

  • Joao_C_Faria , create a new column in production

    new column = countx(filter(DateCalendar, DateCalendar[Date] >= Production[Start Date] && DateCalendar[Date] <= Production[End Date] && DateCalendar[Workday]=1),DateCalendar[Date])

  • First of all, thank you for availability.
    
    Says the expression references multiple columns. It is not possible to transform several columns into a scalar value.
    
    I send the images as an attachment to make it easier, I changed the name of the columns that were in Portuguese to make it more readable.
    
    Compliments
    I need to know the number of business days between startdate and enddate.

    Thank you very much.


    • amitchandak's avatar
      amitchandak
      Super User

      Joao_C_Faria , id start date and end date are column in same table :Production, you can create a column in Production

       

      new column = countx(filter(DateCalendar, DateCalendar[Date] >= Production[Start Date] && DateCalendar[Date] <= Production[End Date] && DateCalendar[Workday]=1),DateCalendar[Date])

       

       

      else you have to take a measure approch

       

      How to calculate Business Days/ Workdays, with or without date table: https://youtu.be/Qv4wT8_P-AA

       

  • The number 1 in the calendar table represents the company being open, and it's in text format, I tried to do "1", but it didn't work either.