DATEDIFF: finding column with most recent date
v-huizhn-msft
Sure Angelia, sorry I did a bad job of explaining.
Not all jobs move in a linear fashion; some will start in Stage 2 (or 3, 4, etc.) and move backwards before forwards.
Example: Job C
Starts in Stage 2 (January 10th, 2018)
Moves to Stage 1 (Feb 14, 2018)
Progresses to Stage 3 (March 12, 2018)
then Stage 4 (Apr 10, 2018)
and finally, Stage 5 (May 22, 2018).
This means the time spent in each Stage is:
Stage 2: 35 days (January 10th to Feb 14)
Stage 1: 26 days (Feb 14th to March 12)
Stage 3: 29 days (March 12 to April 10)
Stage 4: 42 days (April 10 to May 22).
I would like to account for all of these scenarios by creating a calculated column to determine how long each job spent in that stage, before moving on to the next Stage (whether that stage is directly after, 1 -> 2, or not, 3 ->1). Essentially I need to evaluate the 5 columns on a row-by-row basis to determine which column contains the NEXT smallest date, and then use that date for in DATEDIFF.
My current brute-force approach involves determining all permutations that may contain the "next smallest" date, and writing a variable to calculate the minimum of these:
DateMin(2,3,4,5) =
VAR AllDates = {
([Entered 2]),
([Entered 3]),
([Entered 4]),
([Entered 5])
}
VAR MinDate =
MINX ( FILTER( AllDates, [Value] <> 0), [Value] )
RETURN
MINX( FILTER( AllDates, [Value] = MinDate ), [Value] )And then after I have determined all those, writing a massive IF statement. I've only done it for the first Stage (below) so far, and it wasn't fun. There must be a more efficient way!
Velocity: 1 =
// First check if the job has completed. If so, compute time between start and finish
IF([Completed Date] <> 0, DATEDIFF([Entered 1], [Completed Date], DAY),
//Otherwise, check all permutations until position is found
IF([Entered 1] < [DateMin(2,3,4,5)], DATEDIFF([Entered 1], [DateMin(2,3,4,5)], DAY),
IF([Entered 1] < [DateMin(2,3,4)], DATEDIFF([Entered 1], [DateMin(2,3,4)], DAY),
IF([Entered 1] < [DateMin(2,3,5)], DATEDIFF([Entered 1], [DateMin(2,3,5)], DAY),
IF([Entered 1] < [DateMin(2,4,5)], DATEDIFF([Entered 1], [DateMin(2,4,5)], DAY),
IF([Entered 1] < [DateMin(3,4,5)], DATEDIFF([Entered 1], [DateMin(3,4,5)], DAY),
IF([Entered 1] < [DateMin(2,3)], DATEDIFF([Entered 1], [DateMin(2,3)], DAY),
IF([Entered 1] < [DateMin(2,4)], DATEDIFF([Entered 1], [DateMin(2,4)], DAY),
IF([Entered 1] < [DateMin(2,5)], DATEDIFF([Entered 1], [DateMin(2,5)], DAY),
IF([Entered 1] < [DateMin(3,4)], DATEDIFF([Entered SQ], [DateMin(3,4)], DAY),
IF([Entered 1] < [DateMin(3,5)], DATEDIFF([Entered 1], [DateMin(3,5)], DAY),
IF([Entered 1] < [DateMin(4,5)], DATEDIFF([Entered 1], [DateMin(4,5)], DAY),
//If not any of the above, the job is still in Stage 1
DATEDIFF([Entered 1], TODAY(), DAY)
)
)
)
)
)
)
)
)
)
)
)
) Hi Sweet-T,
I understand your scenario now. While there is no permanent logic to find the minimum value at a time. Recursion for is unsupported using DAX, we have to check all permutations until position is found. So it's hard to find a efficient way. PQ M language can deal with the recursion, you can post your thread to specific forum to get more dedicated support.
Thanks,
Angelia