Datediff - Ignore weekends
Hi All I have a very simple visulisation board for vacations. Just for some Engineers (source is Asana) I have a Out of Office Start and an out of office end OOU=Out of Office Hold...
Dangar332
Resident Rockstar
2 years agohi, Anonymous
try below for new column
column =
NETWORKDAYS(table[oou start],table[oou end],1) here 1 for holiday(sat, sun)
2 for holiday(sun, mon)
for measure
measure =
NETWORKDAYS(max(tablename[oou star]),max(tablename[oou end]),1)