Date Diff in Hours : Minutes excluding weekends..

 

Hi I was struggling to calculate the time difference in hours:minutes and have got a perfect solution and it is working perfectly.

 

Is it possible to exclude the weekends while using the below query?

 

Diff2 =
VAR DiffInMinutes =
    DATEDIFF ( Table1[Start]; Table1[End]; MINUTE )
VAR DiffInHours =
    QUOTIENT ( DiffInMinutes; 60 )
VAR ModuloDiffInMinutes =
    MOD ( DiffInMinutes; 60 )
VAR Result =
    FORMAT ( DiffInHours; "00" ) & ":"
        & FORMAT ( ModuloDiffInMinutes; "00" )
RETURN
    Result

 

Nolock  Kindly help...

  • Nolock's avatar
    Nolock
    7 years ago

    Hi Anonymous,

    I've implemented your additional requirements for handling hours at weekends. You need some new columns:

    First of all, you need to find a new Start timestamp. If it is Saturday or Sunday, just use the start of tomorrow.

    NextPossibleStart = 
    IF (
        WEEKDAY ( Table1[Start]; 2 ) >= 6;
        DATEADD ( Table1[Start].[Date]; 1; DAY );
        Table1[Start]
    )

    Then you need to find the start of a day if the end timestamps is Saturday or Sunday.

    PreviousPossibleEnd = 
    VAR IsWeekend =
        WEEKDAY ( Table1[End]; 2 ) >= 6
    VAR NewEndDate =
        IF ( IsWeekend; Table1[End].[Date]; Table1[End] )
    VAR IsNewEndDateBeforeStartDate = NewEndDate < Table1[NextPossibleStart]
    RETURN
        IF ( IsNewEndDateBeforeStartDate; Table1[NextPossibleStart]; NewEndDate )

    Use these 2 new columns in finding all weekend days between 2 dates.

    CountOfWeekdays = 
    VAR tableOfDays =
        CALENDAR ( Table1[NextPossibleStart]; Table1[PreviousPossibleEnd] )
    VAR tableOfWeekdays =
        FILTER ( tableOfDays; WEEKDAY ( [Date]; 2 ) >= 6 )
    VAR countOfWeekdays =
        COUNTROWS ( tableOfWeekdays )
    RETURN
        IF ( ISBLANK ( countOfWeekdays ); 0; countOfWeekdays )

    And also in the diff:

    DiffWithoutWeekends = 
    VAR DiffInMinutes =
        DATEDIFF ( Table1[NextPossibleStart]; Table1[PreviousPossibleEnd]; MINUTE )
    VAR DiffInHours =
        QUOTIENT ( DiffInMinutes; 60 )
    VAR WeekendHours = 24 * Table1[CountOfWeekdays]
    VAR DiffInHoursWithoutWeekend = DiffInHours - WeekendHours
    VAR ModuloDiffInMinutes =
        MOD ( DiffInMinutes; 60 )
    VAR Result =
        FORMAT ( DiffInHoursWithoutWeekend; "00" ) & ":"
            & FORMAT ( ModuloDiffInMinutes; "00" )
    RETURN
        Result

    Some tests:

    And you can also download the PowerBI file again, I've uploaded the new version of it.

6 Replies

  • Nolock's avatar
    Nolock
    Icon for Resident Rockstar rankResident Rockstar

    Hi Anonymous,

    I expect that neither start nor end timestamp is on the weekend. In the other case my code wouldn't work. If it can happen that start or end are at the weekend please explain what behavior you expect.

     

    Create a new column which calculates all weekend days between A and B:

    CountOfWeekdays = 
    VAR tableOfDays = CALENDAR(Table1[Start]; Table1[End])
    VAR tableOfWeekdays = FILTER(tableOfDays; WEEKDAY([Date]; 2) >= 6)
    VAR countOfWeekdays = COUNTROWS(tableOfWeekdays)
    RETURN
    IF(ISBLANK(countOfWeekdays); 0; countOfWeekdays)

    Remove weekends from the difference:

    DiffWithoutWeekends = 
    VAR DiffInMinutes = DATEDIFF(Table1[Start]; Table1[End]; MINUTE)
    VAR DiffInHours = QUOTIENT(DiffInMinutes; 60)
    VAR WeekendHours = 24 * Table1[CountOfWeekdays]
    VAR DiffInHoursWithoutWeekend = DiffInHours - WeekendHours
    VAR ModuloDiffInMinutes = MOD(DiffInMinutes; 60)
    VAR Result = FORMAT(DiffInHoursWithoutWeekend; "00") & ":" & FORMAT(ModuloDiffInMinutes; "00")
    RETURN
    Result

    And the result:

     

    PowerBI file with the solution: PowerBI file

    • Anonymous's avatar
      Anonymous
      Not applicable

      Thank you for replying.. This script is for calculating how much duration is taken to close an IT Ticket excluding weeknd hours.

       

      If the Start falls in weekend then we should exclude the Start Time hours should be excluded while calculating the time difference. Similarly if the End Falls in weekend then End hours should be excluded while calculating the time difference.

       

      Is this possible?

      • Nolock's avatar
        Nolock
        Icon for Resident Rockstar rankResident Rockstar

        Hi Anonymous,

        I've implemented your additional requirements for handling hours at weekends. You need some new columns:

        First of all, you need to find a new Start timestamp. If it is Saturday or Sunday, just use the start of tomorrow.

        NextPossibleStart = 
        IF (
            WEEKDAY ( Table1[Start]; 2 ) >= 6;
            DATEADD ( Table1[Start].[Date]; 1; DAY );
            Table1[Start]
        )

        Then you need to find the start of a day if the end timestamps is Saturday or Sunday.

        PreviousPossibleEnd = 
        VAR IsWeekend =
            WEEKDAY ( Table1[End]; 2 ) >= 6
        VAR NewEndDate =
            IF ( IsWeekend; Table1[End].[Date]; Table1[End] )
        VAR IsNewEndDateBeforeStartDate = NewEndDate < Table1[NextPossibleStart]
        RETURN
            IF ( IsNewEndDateBeforeStartDate; Table1[NextPossibleStart]; NewEndDate )

        Use these 2 new columns in finding all weekend days between 2 dates.

        CountOfWeekdays = 
        VAR tableOfDays =
            CALENDAR ( Table1[NextPossibleStart]; Table1[PreviousPossibleEnd] )
        VAR tableOfWeekdays =
            FILTER ( tableOfDays; WEEKDAY ( [Date]; 2 ) >= 6 )
        VAR countOfWeekdays =
            COUNTROWS ( tableOfWeekdays )
        RETURN
            IF ( ISBLANK ( countOfWeekdays ); 0; countOfWeekdays )

        And also in the diff:

        DiffWithoutWeekends = 
        VAR DiffInMinutes =
            DATEDIFF ( Table1[NextPossibleStart]; Table1[PreviousPossibleEnd]; MINUTE )
        VAR DiffInHours =
            QUOTIENT ( DiffInMinutes; 60 )
        VAR WeekendHours = 24 * Table1[CountOfWeekdays]
        VAR DiffInHoursWithoutWeekend = DiffInHours - WeekendHours
        VAR ModuloDiffInMinutes =
            MOD ( DiffInMinutes; 60 )
        VAR Result =
            FORMAT ( DiffInHoursWithoutWeekend; "00" ) & ":"
                & FORMAT ( ModuloDiffInMinutes; "00" )
        RETURN
            Result

        Some tests: