Create a Table with current week data and previous week data

Hello all,

 

I have a data source table that contains a weekly snapshot of project statuses. The table udates every Tuesday morning and appends with the latest updates. Each row of data includes a field with the update date.

Here's a simplified view of the source data:


Using the source data, I woudl like to create a new table that looks something like this, so I can track and report weekly changes to key project status fields.


Does anyone have any suggestions on the best way to tackle this? I've tried a couple solutions in Power Query, and a couple using DAX to create a virtual table, but just can't make it work. Any detailed suggestions you can offer for a Power Query or DAX solution would be much appreciated!

  • Anonymous's avatar
    Anonymous
    4 years ago

    Hi

    On the second pic you missed a ) to close the calculate function before the coma

    But it does no explain everything. I have put your table name and fields names in the formula try it because here it still working well.

    the new code you can copy

    New Table =
    VAR step1 =
    SUMMARIZE (
    stg_jira_product_team_initiatives_hist,
    stg_jira_product_team_initiatives_hist[Initiative Key]
    )
    RETURN
    GENERATE (
    step1,
    VAR issue = [Initiative Key]
    VAR maxdateupdate =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[spark_created_date] ),
    stg_jira_product_team_initiatives_hist[Initiative Key] = issue
    )
    VAR previousupdatedate =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[spark_created_date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] < maxdateupdate
    )
    VAR curstatus =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[Workflow Status] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevstatus =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[Workflow Status] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    VAR curtarget =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[IP Target Delivery Date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevtarget =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[IP Target Delivery Date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    VAR curryg =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[R/Y/G] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevryg =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[R/Y/G] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    RETURN
    ROW (
    "Update Date", maxdateupdate,
    "Previous Update Date", previousupdatedate,
    "Currenty Status", curstatus,
    "Previous Status", prevstatus,
    "Status change", IF ( curstatus = prevstatus, "No", "Yes" ),
    "Current Target deliver Date", curtarget,
    "Previous Target deliver Date", prevtarget,
    "Target change", IF ( curtarget = prevtarget, "No", "Yes" ),
    "Current R/Y/G Status", curryg,
    "Previous R/Y/G Status", prevryg,
    "R/Y/G change", IF ( curryg = prevryg, "No", "Yes" )
    )
    )

5 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hello,

     

    I have created a table==> Feuil1

    and then I create a new table in Pwbi

    Try it and tell me if it works.

    • Anonymous's avatar
      Anonymous
      Not applicable

      Anonymous Thanks so much for providing this example. I really appreciate your efforts! I have tried to implement it this morning, but I'm running into a few errors:

      First, it doesn't like the IF expressions for the Change columns:

      When I comment those lines out, I then get a error in line 16:

      Any thoughts on what's going on?

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi

    On the second pic you missed a ) to close the calculate function before the coma

    But it does no explain everything. I have put your table name and fields names in the formula try it because here it still working well.

    the new code you can copy

    New Table =
    VAR step1 =
    SUMMARIZE (
    stg_jira_product_team_initiatives_hist,
    stg_jira_product_team_initiatives_hist[Initiative Key]
    )
    RETURN
    GENERATE (
    step1,
    VAR issue = [Initiative Key]
    VAR maxdateupdate =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[spark_created_date] ),
    stg_jira_product_team_initiatives_hist[Initiative Key] = issue
    )
    VAR previousupdatedate =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[spark_created_date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] < maxdateupdate
    )
    VAR curstatus =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[Workflow Status] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevstatus =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[Workflow Status] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    VAR curtarget =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[IP Target Delivery Date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevtarget =
    CALCULATE (
    MAX ( stg_jira_product_team_initiatives_hist[IP Target Delivery Date] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    VAR curryg =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[R/Y/G] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = maxdateupdate
    )
    VAR prevryg =
    CALCULATE (
    VALUES ( stg_jira_product_team_initiatives_hist[R/Y/G] ),
    stg_jira_product_team_initiatives_hist[spark_created_date] = previousupdatedate
    )
    RETURN
    ROW (
    "Update Date", maxdateupdate,
    "Previous Update Date", previousupdatedate,
    "Currenty Status", curstatus,
    "Previous Status", prevstatus,
    "Status change", IF ( curstatus = prevstatus, "No", "Yes" ),
    "Current Target deliver Date", curtarget,
    "Previous Target deliver Date", prevtarget,
    "Target change", IF ( curtarget = prevtarget, "No", "Yes" ),
    "Current R/Y/G Status", curryg,
    "Previous R/Y/G Status", prevryg,
    "R/Y/G change", IF ( curryg = prevryg, "No", "Yes" )
    )
    )
    • Anonymous's avatar
      Anonymous
      Not applicable

      Thanks again Anonymous ! I was able to drop your new code version in, and got the expected results! You are my hero for today!

      • Anonymous's avatar
        Anonymous
        Not applicable

        Hi Benx, No problem happy for you. Have a nice day