Count "1" values in a column

Hi All,

 

I've spent far too many hours today trying to figure out what is probably a simple thing for you all...

 

I have a column in PBI that has either 0 or 1 in it for 200+ rows.  I want to count the "1"'s.  I've tried allsorts and been through all of the questions and answers here but they are far more complicated than this.

The column with the 0 and 1 in is "Start 28d" - please help? This would be simple in Excel: countif(range > 0) or something.

 

Thanks,

Martin

  • Anonymous 

    if the column only has two values,0 and 1, what about use SUM ? The result of SUM is the result of counting 1.

8 Replies

  • Anonymous 

    if the column only has two values,0 and 1, what about use SUM ? The result of SUM is the result of counting 1.

    • Anonymous's avatar
      Anonymous
      Not applicable

      Thanks for this - I should have gotten it, but my mind was set on 'count'.  All working as it should - thank you 🙂

  • Hi,

    try 

    Measure = calculate(count('Table'[Column1]),'Table'[Column1]=1)
    • Anonymous's avatar
      Anonymous
      Not applicable

      Thanks! This worked for one of them (start dates) but gives me an error when trying to replicate for finish dates?

       

      Finish 28d = IF(Task[Finish Next Period] > -28 && Task[Finish Next Period] < 0, 1, 0)
      Finish 28d Qty = CALCULATE ( count (Task[Finish 28d] ),Task[Finish 28d] = 1 )

      Start 28d = IF(Task[Start Next Period] > -28 && Task[Start Next Period] < 0, 1, 0)
      Start 28d qty = CALCULATE ( COUNT ( Task[Start 28d] ), Task[Start 28d] = 1 )

       

       

      • serpiva64's avatar
        serpiva64
        Icon for Solution Sage rankSolution Sage

        Hi,

        i don't think it's a problem of the measure.

        Task[Finish Next Period] or Task[Start Next Period] are calculated columns?