Dear All,

I'm struggling with a simulating scenario issue.
What I have is the following (sample here: https://drive.google.com/drive/folders/1MVy3gaikJeTU0HA9pvtZq503w4BW7b3T?usp=sharing ðŸ˜ž

Through the slicer I am able to select a project and vary the values in "simulating demand".

My problem is that, when I select another project, that value comes back to the original, which is the one in "demand".

 

Is there a way to maintain the simulated values when I'm switching to the other projects?
Maybe the only solution is changing values at the level of source tables, but is there any chance I can do this with a parameter?

Thank you for helping on this.

 

  • Anonymous's avatar
    Anonymous
    4 years ago

    Hi gianmarco ,

     

    According to my understanding,

    1. Firstly you select Project1 and What-if Parameter =0.2 , then simulating demand =120.

    2. When switch to Project2 , Parameter still=0.2, you want to remain Project1 =120 and also show Project2 =60,right?

     

    If the Parameter do not need change, I'd suggest you use multiple selections in slicer at one time and modify you [Measure]:

    Measure = IF(MAX(project[project]) in ALLSELECTED(slicer_project[slicer_project]),MAX(demand[demand])*(1+[Parameter Value]),MAX(demand[demand]))

     

    Best Regards,
    Eyelyn Qin
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

     

3 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi gianmarco ,

     

    According to my understanding,

    1. Firstly you select Project1 and What-if Parameter =0.2 , then simulating demand =120.

    2. When switch to Project2 , Parameter still=0.2, you want to remain Project1 =120 and also show Project2 =60,right?

     

    If the Parameter do not need change, I'd suggest you use multiple selections in slicer at one time and modify you [Measure]:

    Measure = IF(MAX(project[project]) in ALLSELECTED(slicer_project[slicer_project]),MAX(demand[demand])*(1+[Parameter Value]),MAX(demand[demand]))

     

    Best Regards,
    Eyelyn Qin
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.