Burn-Up Chart for Project % Completion
Hi everyone,
Trying to do something that probably isn’t all that difficult but for whatever reason isn’t coming naturally to me.
I’d like to create a “burn-up” chart to show the rate required to achieve 100% completion of all work items by a specified date. Some example data, assuming I get a reading once every 2 days or so (and it doesn’t start at 0 because I didn’t start gathering data until after it was in motion).
Date | % Completed | % Desired |
5/3/2019 | 16.10% |
|
5/5/2019 | 16.10% |
|
5/6/2019 | 17.50% |
|
5/8/2019 | 17.50% |
|
5/10/2019 | 17.50% |
|
5/12/2019 | 18.90% |
|
5/15/2019 | 18.90% |
|
5/16/2019 | 19.50% |
|
5/18/2019 | 23.1% | |
5/20/2019 | 26.82% | |
5/22/2019 | 30.48% | |
5/24/2019 | 34.14% |
And let’s just say I had to get to 100% by 6/30. Would want to project a column/measure that showed the % complete required on each day (basically, the rate required) to make that goal. I’m not sure if the numbers I have there are exactly right, but hopefully you get the idea. Note that currently the % completed in my chart is a calculated measure. Any suggestions?
Hi brianlehr
1.Create a date table
Date table = CALENDARAUTO()
Create relationship as below
2. in Sheet3, create measures as below
lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date]) desireddate = DATE(2019,6,30) period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2 last percent = CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate])) rate = (1-[last percent])/[period] start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate]) data_modified = VAR num = DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2 RETURN IF ( num = INT ( num ) && MAX ( 'Date table'[Date] ) <= [desireddate], IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ), BLANK () ) % Desired = VAR desireddata = SUMX ( FILTER ( ALL ( 'Date table' ), 'Date table'[Date] >= [lastdate] + 2 && 'Date table'[Date] <= [desireddate] && 'Date table'[Date] <= MAX ( 'Date table'[Date] ) + 1 ), [data_modified] ) RETURN IF ( [data_modified] <> BLANK (), desireddata, BLANK () ) final = IF([% Desired]=BLANK(),[% Completed],[% Desired])Best Regards
MaggieCommunity Support Team _ Maggie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
5 Replies
- v-juanli-msft
Community Support
Hi brianlehr
1.Create a date table
Date table = CALENDARAUTO()
Create relationship as below
2. in Sheet3, create measures as below
lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date]) desireddate = DATE(2019,6,30) period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2 last percent = CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate])) rate = (1-[last percent])/[period] start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate]) data_modified = VAR num = DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2 RETURN IF ( num = INT ( num ) && MAX ( 'Date table'[Date] ) <= [desireddate], IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ), BLANK () ) % Desired = VAR desireddata = SUMX ( FILTER ( ALL ( 'Date table' ), 'Date table'[Date] >= [lastdate] + 2 && 'Date table'[Date] <= [desireddate] && 'Date table'[Date] <= MAX ( 'Date table'[Date] ) + 1 ), [data_modified] ) RETURN IF ( [data_modified] <> BLANK (), desireddata, BLANK () ) final = IF([% Desired]=BLANK(),[% Completed],[% Desired])Best Regards
MaggieCommunity Support Team _ Maggie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.- brianlehr
Microsoft Employee
v-juanli-msft This is great! Usually I'm able to follow along, but I will admit that some of this lost me on first glance, but it seems to work. I'll need to study this more to understand. Thanks!
- brianlehr
Microsoft Employee
Sorry, not sure I understand the question? The % desired is what I want to generate as a "burnup".
So to get the sample numbers shown there, I worked out what the % required increase for every data measurement period would be.
I assume 6/30 which was 22 "2-day periods" from the last date with data, so I think you'd need about 3.6% per each period to reach 100% by 6/30.