Burn-Up Chart for Project % Completion

Hi everyone,

 

Trying to do something that probably isn’t all that difficult but for whatever reason isn’t coming naturally to me.

 

I’d like to create a “burn-up” chart to show the rate required to achieve 100% completion of all work items by a specified date.  Some example data, assuming I get a reading once every 2 days or so (and it doesn’t start at 0 because I didn’t start gathering data until after it was in motion).

 

Date

% Completed

% Desired

5/3/2019

16.10%

 

5/5/2019

16.10%

 

5/6/2019

17.50%

 

5/8/2019

17.50%

 

5/10/2019

17.50%

 

5/12/2019

18.90%

 

5/15/2019

18.90%

 

5/16/2019

19.50%

 

5/18/2019

 

23.1%

5/20/2019

 

26.82%

5/22/2019

 

30.48%

5/24/2019

 

34.14%

 

And let’s just say I had to get to 100% by 6/30.  Would want to project a column/measure that showed the % complete required on each day (basically, the rate required) to make that goal.  I’m not sure if the numbers I have there are exactly right, but hopefully you get the idea.  Note that currently the % completed in my chart is a calculated measure.  Any suggestions?

  • Hi brianlehr 

    1.Create a date table

    Date table = CALENDARAUTO()

    Create relationship as below

     

    2. in Sheet3, create measures as below

    lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date])
    
    desireddate = DATE(2019,6,30)
    
    period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2
    
    last percent = 
    CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate]))
    
    rate = (1-[last percent])/[period]
    
    start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate])
    
    data_modified =
    VAR num =
        DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2
    RETURN
        IF (
            num = INT ( num )
                && MAX ( 'Date table'[Date] ) <= [desireddate],
            IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ),
            BLANK ()
        )
    
    % Desired =
    VAR desireddata =
        SUMX (
            FILTER (
                ALL ( 'Date table' ),
                'Date table'[Date] >= [lastdate] + 2
                    && 'Date table'[Date] <= [desireddate]
                    && 'Date table'[Date]
                        <= MAX ( 'Date table'[Date] ) + 1
            ),
            [data_modified]
        )
    RETURN
        IF ( [data_modified] <> BLANK (), desireddata, BLANK () )
    
    final = IF([% Desired]=BLANK(),[% Completed],[% Desired])

    Best Regards
    Maggie

     

    Community Support Team _ Maggie Li
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

5 Replies

  • v-juanli-msft's avatar
    v-juanli-msft
    Icon for Community Support rankCommunity Support

    Hi brianlehr 

    1.Create a date table

    Date table = CALENDARAUTO()

    Create relationship as below

     

    2. in Sheet3, create measures as below

    lastdate = MAXX(FILTER(ALL(Sheet3),[% Completed]<>BLANK()),Sheet3[Date])
    
    desireddate = DATE(2019,6,30)
    
    period = DATEDIFF([lastdate]+1,[desireddate],DAY)/2
    
    last percent = 
    CALCULATE([% Completed],FILTER(ALL(Sheet3),Sheet3[Date]=[lastdate]))
    
    rate = (1-[last percent])/[period]
    
    start = IF(MAX('Date table'[Date])=[lastdate]+2,[last percent]+[rate])
    
    data_modified =
    VAR num =
        DATEDIFF ( [lastdate] + 2, MAX ( 'Date table'[Date] ), DAY ) / 2
    RETURN
        IF (
            num = INT ( num )
                && MAX ( 'Date table'[Date] ) <= [desireddate],
            IF ( MAX ( 'Date table'[Date] ) = [lastdate] + 2, [start], [rate] ),
            BLANK ()
        )
    
    % Desired =
    VAR desireddata =
        SUMX (
            FILTER (
                ALL ( 'Date table' ),
                'Date table'[Date] >= [lastdate] + 2
                    && 'Date table'[Date] <= [desireddate]
                    && 'Date table'[Date]
                        <= MAX ( 'Date table'[Date] ) + 1
            ),
            [data_modified]
        )
    RETURN
        IF ( [data_modified] <> BLANK (), desireddata, BLANK () )
    
    final = IF([% Desired]=BLANK(),[% Completed],[% Desired])

    Best Regards
    Maggie

     

    Community Support Team _ Maggie Li
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

    • brianlehr's avatar
      brianlehr
      Icon for Microsoft Employee rankMicrosoft Employee

      v-juanli-msft This is great!  Usually I'm able to follow along, but I will admit that some of this lost me on first glance, but it seems to work.  I'll need to study this more to understand.  Thanks!

    • brianlehr's avatar
      brianlehr
      Icon for Microsoft Employee rankMicrosoft Employee

      Sorry, not sure I understand the question?   The % desired is what I want to generate as a "burnup".

       

      So to get the sample numbers shown there, I worked out what the % required increase for every data measurement period would be.

       

      I assume 6/30 which was 22 "2-day periods" from the last date with data, so I think you'd need about 3.6% per each period to reach 100% by 6/30.