Hi Expert,

 

I am working on an audit plan, and my data set

 

  1. Have - Audit Name, Task Name, End Date(Due Date), FieldWork Date
  2. don't have - Start Date 

Now, every audit has 34 end dates and I need to create a logic from which I can get the start date for that task. Now what I think - Every audit task 2 start date will be the end date of task 1 and task 1 start date will be task 1 due date - 5 days.

 

I am using the logic below, but it is not working and any help is appreciated.

 

Start Date =
VAR Project = 'Audit Milestones'[Audit Name]
VAR TaskStartDate = 'Audit Milestones'[Due Date]
VAR nextTaskDate =
MINX(
FILTER('Audit Milestones', 'Audit Milestones'[Audit Name] = Project
&& 'Audit Milestones'[Due Date] > TaskStartDate
// && 'Audit Milestones'[Due Date] > TaskStartDate//
),
aud
)
Return
IF(ISBLANK(nextTaskDate), TaskStartDate, nextTaskDate)

 

Project NameTask Field Work Start DateDue DateStart Date ( Logic Required)
P1T125/1/2312/1/23T1 Due Date - 5 days
P1T2 25/1/2315/1/23T1 Due Date
P1T3  25/1/2320/1/23T2 Due Date
P1T4 25/1/23 25/1/23= Field Work Start Date
P1T5 10/1/2325/2/23T4 Due Date
P2T130/1/2314/1/23T1 Due Date - 5 days
P2T130/1/2324/1/23T1 Due Date

 

 

 
  • Hi shefalinishad11 

     

    You can create a new column with this DAX

    Start Date = 
    var _previousDueDate = MAXX(FILTER('Table', 'Table'[Project Name]=EARLIER('Table'[Project Name]) && 'Table'[Due Date]<EARLIER('Table'[Due Date])),'Table'[Due Date])
    return
    IF(ISBLANK(_previousDueDate),'Table'[Due Date]-5,_previousDueDate)

     

    I don't know why the start date for P1's Task 4 should be the Field Work Start Date in your example. With above DAX, it still uses previous task's Due Date as the start date. 

     

    Best Regards,
    Community Support Team _ Jing
    If this post helps, please Accept it as Solution to help other members find it.

1 Reply

  • v-jingzhang's avatar
    v-jingzhang
    Icon for Community Support rankCommunity Support

    Hi shefalinishad11 

     

    You can create a new column with this DAX

    Start Date = 
    var _previousDueDate = MAXX(FILTER('Table', 'Table'[Project Name]=EARLIER('Table'[Project Name]) && 'Table'[Due Date]<EARLIER('Table'[Due Date])),'Table'[Due Date])
    return
    IF(ISBLANK(_previousDueDate),'Table'[Due Date]-5,_previousDueDate)

     

    I don't know why the start date for P1's Task 4 should be the Field Work Start Date in your example. With above DAX, it still uses previous task's Due Date as the start date. 

     

    Best Regards,
    Community Support Team _ Jing
    If this post helps, please Accept it as Solution to help other members find it.