I am being asked to create a calculated RYG for each project and as part of that, I've created table that provides a KPI for scope (measuring how far over or under).  From this KPI, we generate a score using a calculated column

c_Scope Score =
SWITCH(
TRUE(),
'BurndownScope'[Ratio]<=1.3,1,
'BurndownScope'[Ratio]<=1.5,2,
'BurndownScope'[Ratio]>1.5,3
)
 
I then created a calculated column that adds the 4 components of the RYG together to generate an overall score.  The problem I'm running into is with the scope score.  Because it is a column, I can't add it w/o some sort of aggregator, which then gives me the wrong number for the overall score.  How do I pass the scope score for each project to the calculation for the Overall Project score?
 
Dax for overall project score metric
c_Overall Project Score =
'Risks'[m_Project Risk Score]
+
'Issues'[m_Project Issue Score]
+
'Projects'[M_Sched Perf]
+
'burndownscope'[c_Scope Score]

3 Replies

  • The table that has the burn down scope looks like this:

    There's only one value for each project so I'm not clear as to why I need an aggregator?


    Clint wrote:

    Hello,

     

    I am being asked to create a calculated RYG for each project and as part of that, I've created table that provides a KPI for scope (measuring how far over or under).  From this KPI, we generate a score using a calculated column

    c_Scope Score =
    SWITCH(
    TRUE(),
    'BurndownScope'[Ratio]<=1.3,1,
    'BurndownScope'[Ratio]<=1.5,2,
    'BurndownScope'[Ratio]>1.5,3
    )
     
    I then created a calculated column that adds the 4 components of the RYG together to generate an overall score.  The problem I'm running into is with the scope score.  Because it is a column, I can't add it w/o some sort of aggregator, which then gives me the wrong number for the overall score.  How do I pass the scope score for each project to the calculation for the Overall Project score?
     
    Dax for overall project score metric
    c_Overall Project Score =
    'Risks'[m_Project Risk Score]
    +
    'Issues'[m_Project Issue Score]
    +
    'Projects'[M_Sched Perf]
    +
    'burndownscope'[c_Scope Score]

     

  • v-juanli-msft's avatar
    v-juanli-msft
    Icon for Community Support rankCommunity Support

    Hi Clint 

    What is the relationship amonth the four tables?

    'Risks',Issues',Projects',burndownscope'
     
    When adding four columns in one table visual, how does it look like?
    'Risks'[m_Project Risk Score]
    'Issues'[m_Project Issue Score]
    'Projects'[M_Sched Perf]
    'burndownscope'[c_Scope Score]
     

    Could you give some data samples so that i can reproduce your problem?

     

    Best Regards
    Maggie

     

     

    • Clint's avatar
      Clint
      Icon for Helper V rankHelper V

      Hi Maggie,

       

      Risk and Issues are related to the Projects Table via the ProjectID field.  The scope score is generated from a table that tracks the current scope and baseilne scope and is related to a table that tracks weekly burndown (and provides scope values) via the clarity ID in a many to one.  The Burdowns table is related to the Project Table via the Clarity ID (see embedded image).  This is a many to many relationship unfortunately.  

      I am using the "average" function to generate the overall project score in the Project Score table.

      Project Score

       

      Relationships