undefined

Hi ,

 

I have a Slicer that shows date as Between . 

Here i have selected 6 days as my search period .
How can i get the selected date period as Start date and End date Dax Query ? 

  • The  date field you are using in the slicer should come from the date table. I think you don't have date table. If you use a date table you will be much happier in the future. I will paste code for a Date table. If you go to Modeling>New Table> then put the code in. Afterwhich you Mark the Date Table by selecting the Date field and validating on this. Then you connect your Date Table to your sheet one on Date Table Date to Sheet1 Date.

    Then don't use the Sheet1 date field anymore. Use Date Table date field. I hope this makes sense.

    Here is Date Table Code to start with:

    Dates =

     

    -- Specify a start date and end date

    VAR StartDate = Date(2021,1,1)

    VAR EndDate = Today()

    VAR FiscalMonthEnd = 6

     

    -- Generate a base table of dates

    VAR BaseTable = Calendar(StartDate, EndDate)

     

    -- Add the Year for each individual date

    VAR Years = ADDCOLUMNS(BaseTable,"Year",YEAR([Date]))

     

    -- Add the calendar month and other month related data for each date

    VAR Months = ADDCOLUMNS(

        Years,

        "Month",MONTH([Date]),

        "Year and Month Number",FORMAT([Date],"YYYY-MM"),

        "Year and Month Name",FORMAT([Date],"YYYY-MMM"),

        "Fiscal Year", IF( FiscalMonthEnd = 12, YEAR([Date]), IF( MONTH([DATE]) <= FiscalMonthEnd, YEAR([DATE])-1, YEAR([Date]))),

        "Fiscal Month", IF( FiscalMonthEnd = 12, MONTH([Date]),

            IF( MONTH([Date]) <= FiscalMonthEnd, FiscalMonthEnd + MONTH([Date]), MONTH([Date]) - FiscalMonthEnd))

    )

     

    -- Add the Quarter and other quarter related data for each date   

    VAR Quarters = ADDCOLUMNS(

        Months,

        "Quarter",ROUNDUP(MONTH([Date])/3,0),

        "Year and Quarter",[Year] & "-Q" & ROUNDUP(MONTH([Date])/3,0))

     

    -- Add the Day and other day related data for each date   

    VAR Days = ADDCOLUMNS(

        Quarters,

        "Day",DAY([Date]),

        "Day Name",FORMAT([Date],"DDDD"),

        "Day Of Week",WEEKDAY([Date]),

        "Day Of Year", DATEDIFF (DATE(YEAR([Date]),1,1), [Date], DAY) + 1)

     

    -- Add the Week (assuming each week starts on a Sunday) and other week related data for each date   

    VAR Weeks = ADDCOLUMNS(

        Days,

        "Week Of Month (Sunday)",INT((DAY([Date])-1)/7)+1,

        "Week of Year (Sunday)",WEEKNUM([Date],1),

        "Year and Week (Sunday)",[Year] & "-W" & WEEKNUM([Date],1))

     

    -- Add an 'Is Working Day' column which will be true for all days but Saturday and Sunday.

    var WorkingDays = ADDCOLUMNS(

        Weeks,

        "Is Working Day", NOT WEEKDAY( [Date] ) IN {1,7})

     

    RETURN WorkingDays

     

    Model should look like this:

     

11 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable
    i cannot achieve the expected output with FIRSTDATE , LASTDATE options  .

    Any Suggessions ? my expected output was start date = 3/6/2022 , end date = 3/12/2022
     
    Please Help 

     

  • tamerj1's avatar
    tamerj1
    Community Champion

    Hi Anonymous 

    you can use

    Start Date = MINX ( ALLSELECTED (  DateTable ), DateTable[Date] )

    or

    Start Date = CALCULATE ( MIN ( DateTable[Date] ), ALLSELECTED ( DateTable ) )

    same for End Date but with MAXX or MAX

    • Anonymous's avatar
      Anonymous
      Not applicable

      Hi , Thanks for the reply .

       

      But both MINX  and CALCULATE ( MIN functions gives 7 not the min date of selected range . in my case the selected min date is 6th 

       

      • tamerj1's avatar
        tamerj1
        Community Champion

        Anonymous 

        Do you have date table? Would you please paste the code you have used?

  • Hi:

    With a date table.

    Start = Calculate(MIN(Dates[Date]))
    End = CALCULATE(MAX(Dates[Date]))

     

    • Anonymous's avatar
      Anonymous
      Not applicable

      Hi , 

       

      why the answers differs ?? 

      • Whitewater100's avatar
        Whitewater100
        Solution Sage

        The  date field you are using in the slicer should come from the date table. I think you don't have date table. If you use a date table you will be much happier in the future. I will paste code for a Date table. If you go to Modeling>New Table> then put the code in. Afterwhich you Mark the Date Table by selecting the Date field and validating on this. Then you connect your Date Table to your sheet one on Date Table Date to Sheet1 Date.

        Then don't use the Sheet1 date field anymore. Use Date Table date field. I hope this makes sense.

        Here is Date Table Code to start with:

        Dates =

         

        -- Specify a start date and end date

        VAR StartDate = Date(2021,1,1)

        VAR EndDate = Today()

        VAR FiscalMonthEnd = 6

         

        -- Generate a base table of dates

        VAR BaseTable = Calendar(StartDate, EndDate)

         

        -- Add the Year for each individual date

        VAR Years = ADDCOLUMNS(BaseTable,"Year",YEAR([Date]))

         

        -- Add the calendar month and other month related data for each date

        VAR Months = ADDCOLUMNS(

            Years,

            "Month",MONTH([Date]),

            "Year and Month Number",FORMAT([Date],"YYYY-MM"),

            "Year and Month Name",FORMAT([Date],"YYYY-MMM"),

            "Fiscal Year", IF( FiscalMonthEnd = 12, YEAR([Date]), IF( MONTH([DATE]) <= FiscalMonthEnd, YEAR([DATE])-1, YEAR([Date]))),

            "Fiscal Month", IF( FiscalMonthEnd = 12, MONTH([Date]),

                IF( MONTH([Date]) <= FiscalMonthEnd, FiscalMonthEnd + MONTH([Date]), MONTH([Date]) - FiscalMonthEnd))

        )

         

        -- Add the Quarter and other quarter related data for each date   

        VAR Quarters = ADDCOLUMNS(

            Months,

            "Quarter",ROUNDUP(MONTH([Date])/3,0),

            "Year and Quarter",[Year] & "-Q" & ROUNDUP(MONTH([Date])/3,0))

         

        -- Add the Day and other day related data for each date   

        VAR Days = ADDCOLUMNS(

            Quarters,

            "Day",DAY([Date]),

            "Day Name",FORMAT([Date],"DDDD"),

            "Day Of Week",WEEKDAY([Date]),

            "Day Of Year", DATEDIFF (DATE(YEAR([Date]),1,1), [Date], DAY) + 1)

         

        -- Add the Week (assuming each week starts on a Sunday) and other week related data for each date   

        VAR Weeks = ADDCOLUMNS(

            Days,

            "Week Of Month (Sunday)",INT((DAY([Date])-1)/7)+1,

            "Week of Year (Sunday)",WEEKNUM([Date],1),

            "Year and Week (Sunday)",[Year] & "-W" & WEEKNUM([Date],1))

         

        -- Add an 'Is Working Day' column which will be true for all days but Saturday and Sunday.

        var WorkingDays = ADDCOLUMNS(

            Weeks,

            "Is Working Day", NOT WEEKDAY( [Date] ) IN {1,7})

         

        RETURN WorkingDays

         

        Model should look like this: