Hi All,
I'd like to know if there is a way to calculate networkdays between two different days with time i.e.
[Creation Date] is 11/23/2021 3:30 pm
[Completion Date] is 12/06/2021 9:04 am
and the result Id like to have in format : 10.75 days
Could you advise/help or redirect to correct post about this topic ? Thanks. Maciej
// Something like this. // Dates is a calendar that stores // full days (with no time component). |---------|=====A=====|==========|---------|==========|---------|==========|----B----| // Legend: |====| -> non-working day, |---| -> working day var DateTime1 = A var Date1 = DATEVALUE( DateTime1 ) var DateTime2 = B var Date2 = DATEVALUE( DateTime2 ) var FirstWorkingAfterOrOnA = CALCULATE( MIN( Dates[Date] ), Dates[Date] >= Date1, Dates[Day Type] = "working" ) var LastWorkingBeforeOrOnB = CALCULATE( MAX( Dates[Date] ), Dates[Date] <= Date2, Dates[Day Type] = "working" ) var StartDate = MAX( DateTime1, FirstWorkingAfterOrOnA ) var EndDate = MIN( DateTime2, LastWorkingBeforeOrOnB ) var NonworkingDays = CALCULATE( COUNTROWS( Dates ), Dates[Date] >= StartDate, Dates[Date] <= EndDate, Dates[Day Type] = "non-working" ) var NetworkingDays = 1 * (EndDate - StartDate) - NonworkingDays var Result = IF( NetworkingDays > 0, NetWorkingdays ) return Result
4 Replies
- daXtremeSolution Sage
1 * ([Completion Date] - [Creation Date])
- AnonymousNot applicable
This would not help . Networkdays are working days.
- daXtremeSolution Sage
// Something like this. // Dates is a calendar that stores // full days (with no time component). |---------|=====A=====|==========|---------|==========|---------|==========|----B----| // Legend: |====| -> non-working day, |---| -> working day var DateTime1 = A var Date1 = DATEVALUE( DateTime1 ) var DateTime2 = B var Date2 = DATEVALUE( DateTime2 ) var FirstWorkingAfterOrOnA = CALCULATE( MIN( Dates[Date] ), Dates[Date] >= Date1, Dates[Day Type] = "working" ) var LastWorkingBeforeOrOnB = CALCULATE( MAX( Dates[Date] ), Dates[Date] <= Date2, Dates[Day Type] = "working" ) var StartDate = MAX( DateTime1, FirstWorkingAfterOrOnA ) var EndDate = MIN( DateTime2, LastWorkingBeforeOrOnB ) var NonworkingDays = CALCULATE( COUNTROWS( Dates ), Dates[Date] >= StartDate, Dates[Date] <= EndDate, Dates[Day Type] = "non-working" ) var NetworkingDays = 1 * (EndDate - StartDate) - NonworkingDays var Result = IF( NetworkingDays > 0, NetWorkingdays ) return Result
- AnonymousNot applicable
Hi Anonymous,
Can you please share a pbix or some dummy data that keep raw data structure with expected results? It should help us clarify your scenario and test to coding formula.
How to Get Your Question Answered Quickly
Regards,