Forum Discussion

MJDS's avatar
MJDS
Frequent Visitor
1 year ago
Solved

Networkdays function is adding an extra day

I'm trying to add a measure to calculate the number of working days between two dates, but the measure I've built adds an extra day. 0 days shows as 1 working days, 1 day as 2 working days and so on....
  • sjoerdvn's avatar
    1 year ago

    Stumbled upon this yesterday, too. The documentation says "Returns the number of whole workdays between two dates (inclusive)." So "inclusive" means including the start date. My solutution was to simply subtract one day.