Forum Discussion

snehar's avatar
snehar
Frequent Visitor
3 years ago

how to get future weeks value

hi friends, 
I want to get planned value for future weeks.
I have planned value table with all data(week and corresponding PV value for each project also for future week)
and also I have project table with data of each project and earned value of each week,(which has data upto current week)
also I have calender table . both table is connected to week num of calender. but when I add all data to visual it only shows upto current week and not future weeks of pv.
how to solve this. Any help would be appreciated:)

3 Replies

    • snehar's avatar
      snehar
      Frequent Visitor

      how to get for future week like202338 or 202348

       

  • snehar's avatar
    snehar
    Frequent Visitor

    in project table the date is upto current week and from that date week and year is calculated and connected with calender week and year
    is this wrong and is that the reason why its getting restricted to current week or my mapping is wrong?