Excluding weekend days from formula

Hi all,    i'm trying to create a measure which shows me the % illness in a month/year, etc. I created the following measure which shows me the days that resources have been ill (based on start an...
  • Anonymous's avatar
    Anonymous
    3 years ago

    Hi Anonymous ,

    You can create a calculated column as below in the table 'resource' to get the number of working days:

    # Days ill =
    CALCULATE (
        COUNTROWS ( 'DimDatum' ),
        FILTER ( 'DimDatum', 'DimDatum'[Is_Weekend] = "false" ),
        DATESBETWEEN ( 'DimDatum'[Date], 'resource'[Start Date], 'resource'[End Date] )
    )

    If the above one can't help you get the desired result, please provide some raw data in your table 'resource' (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. You can refer the following link to upload the file to the community. Thank you.

    How to upload PBI in Community

    Best Regards