hi Rosh88
I have a disconnected CALENDAR Table, please note that I have True/False(Boolean) in IsWorkingDay, you can change DAX to 'CALENDAR'[IsWorkingDay] = 1 instead of just 'CALENDAR'[IsWorkingDay]
This is a calculated column
CompletionDate =VAR _StartDate = 'Fact'[StartDate]VAR _WorkingDays = 'Fact'[WorkingDays]VAR _FltrTable = FILTER('CALENDAR', 'CALENDAR'[IsWorkingDay] && 'CALENDAR'[Date] >= _StartDate)VAR _WorkingDaysTbl =ADDCOLUMNS(_FltrTable,"@RANK",RANK(DENSE, _FltrTable, ORDERBY('CALENDAR'[Date])))RETURN MAXX( FILTER(_WorkingDaysTbl, [@RANK] = _WorkingDays), [Date])
hi Rosh88
I have a disconnected CALENDAR Table, please note that I have True/False(Boolean) in IsWorkingDay, you can change DAX to 'CALENDAR'[IsWorkingDay] = 1 instead of just 'CALENDAR'[IsWorkingDay]
This is a calculated column
Hi Rosh88
I came up with a solution adding a [WorkdayOffset] column to my Date table.
First I added a [IsWeekday] calculated column to my Date table.
IsWeekday = IF( WEEKDAY( [Date], 2 ) > 5, 0, 1 )
Then I added my [WorkdayOffset] column to my Date table. This is to keep track of workdays.
WorkdayOffset =
VAR _Curr = [Date]
VAR _Table =
FILTER(
SUMMARIZE(
ALL( 'Date' ),
'Date'[Date],
'Date'[IsWeekday]
),
'Date'[IsWeekday] = 1
)
VAR _Min =
IF(
_Curr < TODAY(),
_Curr,
TODAY()
)
VAR _Max =
IF(
_Curr < TODAY(),
TODAY(),
_Curr
)
VAR _Count =
COUNTROWS(
FILTER(
_Table,
[Date] >= _Min
&& [Date] <= _Max
)
) - 1
VAR _Logic =
IF(
_Curr >= TODAY(),
_Count,
_Count * -1
)
RETURN
_Logic
Finally, I added a [Completion Date] calculated column to the main table.
Completion Date =
VAR _Start = [StartDate]
VAR _WorkDays = [WorkingDays]
VAR _StartOffset =
CALCULATE(
MAX( 'Date'[WorkdayOffset] ),
'Date'[Date] = _Start
)
VAR _End =
CALCULATE(
MAX( 'Date'[Date] ),
'Date'[WorkdayOffset] = _StartOffset + _WorkDays - 1
)
RETURN
_End