Determining the Completion Date Based on the Start Date + <xx> Working Days
Hi, I am currently working with two specific tables: a Fact Table and a Calendar Table. My objective is to accurately calculate the completion date for each entry. The formula to determine the comp...
- 2 years ago
hi Rosh88
I have a disconnected CALENDAR Table, please note that I have True/False(Boolean) in IsWorkingDay, you can change DAX to 'CALENDAR'[IsWorkingDay] = 1 instead of just 'CALENDAR'[IsWorkingDay]
This is a calculated column
CompletionDate =VAR _StartDate = 'Fact'[StartDate]VAR _WorkingDays = 'Fact'[WorkingDays]VAR _FltrTable = FILTER('CALENDAR', 'CALENDAR'[IsWorkingDay] && 'CALENDAR'[Date] >= _StartDate)VAR _WorkingDaysTbl =ADDCOLUMNS(_FltrTable,"@RANK",RANK(DENSE, _FltrTable, ORDERBY('CALENDAR'[Date])))RETURN MAXX( FILTER(_WorkingDaysTbl, [@RANK] = _WorkingDays), [Date])