Hi All, I want to calculate the End date of a project based on the no. of working days. So the formula currently i have is Today + Total no. of days. Eg: End Date = 20/05/2025 + 10 days = 30...
- 1 year ago
Hearty Thanks for all your support. I tried everyones suggestion but faced some issue. I was able to crack the formula with some help. Below is the DAX:
VAR RemainingDays = A FormulaVAR TodayDate = TODAY()-1RETURNCALCULATE (MAX('Dates'[Date]),FILTER (ADDCOLUMNS (FILTER ('Dates','Dates'[Date] >= TodayDate &&'Dates'[IsWorkingDay] = TRUE),"WorkDayIndex", RANKX (FILTER ('Dates','Dates'[Date] >= TodayDate &&'Dates'[IsWorkingDay] = TRUE),'Dates'[Date],,ASC)),[WorkDayIndex] = RemainingDays))I have a Date table which has a column [IsWorkingDay] =IF (WEEKDAY('Dates'[Date], 2) <= 5, // Monday = 1, ..., Friday = 5TRUE,FALSE)Regards,Amit Wairkar
v-echaithra
Community Support
1 year agoHi amit_wairkar ,
As we haven’t heard back from you, we wanted to kindly follow up to check if the solution provided for the issue worked? or Let us know if you need any further assistance?
If our response addressed, please mark it as Accept as solution and click Yes if you found it helpful.
Regards,
Chaithra.